17708 W RHODA ST 91316

Certificate Information: 17708 W RHODA ST 91316

Application / Permit
21010-20000-00612
Plan Check / Job No.
B21VN01517
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'9" X 25'9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 12/21/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 REZA HAGHIGHAT
Corrections Issued 3/15/2021 REZA HAGHIGHAT
Applicant returned to address corrections 9/9/2021 PINANK PATEL
Plan Check Approved 9/10/2021 PINANK PATEL
Building Plans Picked Up 9/13/2021 APPLICANT
Issued 12/21/2021 APPLICANT
CofO in Progress 8/4/2022 SEAN HAUPT
CofO Issued 8/27/2022 MICHAEL SMITH
Permit Finaled 8/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/22/2021 ADRIAN CASTRO
ZI Cleared 3/24/2021 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 4/23/2021 ADRIAN CASTRO
Sewer availability Cleared 4/23/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 5/7/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/4/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/18/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/10/2021 JEFF FOLLIN

Contact Information

Contractor Idea Fix Construction; Lic. No.: 906459-B 7715 SEDAN AVE      WEST HILLS, CA 91304

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/7/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 1/18/2022 Approved SEAN HAUPT
Underground Mechanical 1/18/2022 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/8/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 4/8/2022 Approved SEAN HAUPT
Green Building Rough 4/8/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 4/8/2022 Approved SEAN HAUPT
PLUMBING-Rough 4/8/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 4/8/2022 Approved SEAN HAUPT
Insulation 4/26/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 4/26/2022 Approved SEAN HAUPT
Drywall Nailing 5/5/2022 Approved SEAN HAUPT
Green Building Rough 5/5/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/5/2022 Approved SEAN HAUPT
Shower Pan 5/5/2022 Approved SEAN HAUPT
ELECTRICAL-Final 7/28/2022 Approved SEAN HAUPT
Final 7/28/2022 Corrections Issued SEAN HAUPT
Green Building Final 7/28/2022 Approved SEAN HAUPT
HVAC-Final 7/28/2022 Approved SEAN HAUPT
MERV13>=Final 7/28/2022 Approved SEAN HAUPT
PLUMBING-Final 7/28/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 7/28/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 7/28/2022 Approved SEAN HAUPT
Final 8/4/2022 OK to Issue CofO SEAN HAUPT
Service/Power Release 8/4/2022 Approved SEAN HAUPT