3870 S CLOVERDALE AVE 90008
Certificate Information: 3870 S CLOVERDALE AVE 90008
- Application / Permit
- 21010-20000-00604
- Plan Check / Job No.
- B21VN01495
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-0" x 40'-8" ONE-STORY DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | SEAN SHAHMIRI |
| Corrections Issued | 2/27/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/3/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/4/2021 | APPLICANT |
| Applicant returned to address corrections | 7/20/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/29/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 8/10/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 8/27/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 9/2/2021 | SEAN SHAHMIRI |
| Issued | 10/8/2021 | APPLICANT |
| CofO in Progress | 3/30/2023 | ANTHONY EGSON |
| Permit Finaled | 4/4/2023 | DEROLD HAUFF |
| CofO Issued | 4/4/2023 | DEROLD HAUFF |
| Permit Finaled | 4/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | JUAN ASHTON |
| Grading Pre-Inspection | Cleared | 4/1/2021 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 5/7/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 6/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/30/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/2/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/3/2021 | WALLIE JONG |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | 12069 SMALLWOOD AVE DOWNEY, CA 90242 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2021 | Corrections Issued | ANTHONY EGSON |
| Special/Order Compliance | 10/18/2021 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 11/15/2021 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/24/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/17/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/17/2022 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 5/25/2022 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 5/26/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/2/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/7/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/10/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/13/2022 | Approved | ANTHONY EGSON |
| Sewer | 11/16/2022 | Partial Approval | ANTHONY EGSON |
| Final | 2/14/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 2/14/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 2/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 2/14/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | SABAS ALONSO |
| Final | 2/27/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/27/2023 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 2/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 2/27/2023 | Approved | ANTHONY EGSON |
| Final | 3/22/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/22/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 3/22/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 3/29/2023 | Approved | ANTHONY EGSON |
| Final | 3/29/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 3/29/2023 | Approved | ANTHONY EGSON |
| Final | 4/14/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 4/24/2023 | OK to Issue CofO | ANTHONY EGSON |