635 N ERSKINE DR 90272
Certificate Information: 635 N ERSKINE DR 90272
- Application / Permit
- 21010-20000-00599
- Plan Check / Job No.
- B21VN01461
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT OVER 4-CAR GARAGE PER LAMC12.22A33(c)(d) (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/2/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/2/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 7/20/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/23/2022 | NILOOFAR MEHRAIN |
| Issued | 9/9/2022 | APPLICANT |
| CofO in Progress | 5/11/2023 | MICHAEL PELHAM |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
| CofO Issued | 5/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 4/12/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/12/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 5/20/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/27/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 2/2/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | DINAH GARIN |
| Coastal Zone | Cleared | 6/28/2022 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 6/28/2022 | RUBEN VASQUEZ |
| ZI | Cleared | 6/28/2022 | RUBEN VASQUEZ |
| GPI Written Notices | Cleared | 7/20/2022 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 7/20/2022 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2022 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/6/2022 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 10/14/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 10/14/2022 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 10/14/2022 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 12/21/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 12/21/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/6/2023 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 1/6/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/6/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/9/2023 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 1/9/2023 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 1/9/2023 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 1/9/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/18/2023 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 1/18/2023 | Approved | MICHAEL PELHAM |
| Insulation | 1/18/2023 | Approved | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 1/18/2023 | Approved | MICHAEL PELHAM |
| Shower Pan | 2/6/2023 | Approved | BRENDAN LOONEY |
| Gas Test | 2/13/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/13/2023 | Approved | BRENDAN LOONEY |
| Gas Test | 2/15/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 3/9/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 3/9/2023 | Approved | BRENDAN LOONEY |
| Service/Power Release | 3/9/2023 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 3/9/2023 | Approved | BRENDAN LOONEY |
| Service/Power Release | 3/21/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/30/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 3/30/2023 | Approved | JESUS PINEDA |
| Smoke Detectors | 3/30/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/17/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 4/17/2023 | Approved | BRENDAN LOONEY |
| Final | 5/3/2023 | Conditional Approval | BRENDAN LOONEY |
| Green Building Final | 5/3/2023 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | BRENDAN LOONEY |