462 N FORMOSA AVE 90036

Certificate Information: 462 N FORMOSA AVE 90036

Application / Permit
21010-20000-00552
Plan Check / Job No.
B21VN01321
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'-4" X 25'-1" (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 1/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 SELLA BENYAMIN
Corrections Issued 3/2/2021 SELLA BENYAMIN
Quality Review Completed 3/10/2021 STEVEN KIM
Building Plans Picked Up 3/11/2021 APPLICANT
Plan Check Approved 8/27/2021 SELLA BENYAMIN
Issued 10/7/2021 APPLICANT
CofO in Progress 1/18/2024 LILIANA PORTILLO
Permit Finaled 1/28/2024 DEROLD HAUFF
CofO Issued 1/28/2024 DEROLD HAUFF
Permit Finaled 1/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 CELINA MORENO
Sewer availability Cleared 4/6/2021 CELINA MORENO
Hydrant and Access approval Cleared 5/14/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/5/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/11/2021 RENZ SORIANO

Contact Information

Contractor Current Trend Contractors Inc; Lic. No.: 476743-B 28366 AGOURA ROAD      AGOURA HILLS, CA 91301
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2021 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 12/21/2021 Not Ready for Inspection CRAIG DAVIS
METHANE-Barrier 12/21/2021 Not Ready for Inspection CRAIG DAVIS
METHANE-Subgrade 12/21/2021 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Corrections Issued ADAM ESCOTO
Underground Mechanical 6/13/2022 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 12/7/2022 Not Ready for Inspection MICHAEL LEWIS
HVAC-Rough 12/7/2022 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 12/7/2022 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 12/8/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 12/8/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/20/2022 Approved MICHAEL LEWIS
Green Building Rough 12/20/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/20/2022 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 12/20/2022 Approved MICHAEL LEWIS
METHANE-Rough 12/20/2022 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 12/20/2022 Approved MICHAEL LEWIS
Insulation 1/10/2023 Conditional Approval MICHAEL LEWIS
Drywall Nailing 1/19/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/19/2023 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Final 10/24/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 10/24/2023 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Final 11/15/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 11/15/2023 Approved LILIANA PORTILLO
PLUMBING-Final 11/15/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 11/15/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 11/17/2023 Conditional Approval LILIANA PORTILLO
Final 11/17/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 11/17/2023 Approved LILIANA PORTILLO
Service/Power Release 11/17/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 12/13/2023 Approved LILIANA PORTILLO
Final 12/13/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/13/2023 Approved LILIANA PORTILLO
Green Building Final 12/13/2023 Approved LILIANA PORTILLO
METHANE-Barrier 12/13/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 12/13/2023 Approved LILIANA PORTILLO
Service/Power Release 12/13/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/13/2023 Approved LILIANA PORTILLO
Final 1/12/2024 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 1/12/2024 Not Ready for Inspection LILIANA PORTILLO
Final 1/17/2024 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 1/17/2024 Approved LILIANA PORTILLO