6244 N LONGRIDGE AVE 91401
Certificate Information: 6244 N LONGRIDGE AVE 91401
- Application / Permit
- 21010-20000-00549
- Plan Check / Job No.
- B21VN01308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-0" X 34'-0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT WITH PORCH PER LAMC 12.22 A.33(c) and (d) . ALL WORK DONE PER ENGINEERING. ***ASSUMPTION OF RISK AGREEMENT FOR DEFERRAL OF LOW IMPACT DEVELOPMENT PROVIDED***
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 2/13/2021 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 1/7/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Applicant returned to address corrections | 5/14/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 8/22/2022 | JOSEPH RAFOLS |
| Issued | 8/22/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | KIRK SANDERS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
| CofO Issued | 10/23/2023 | RUBEN SALAS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/16/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/8/2022 | LARRY REDDEN |
| Roof/Waste drainage to street | Cleared | 8/19/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kyupelyan,, Emil; Lic. No.: C91238 | 8045 LASAINE AVE NORTHRIDGE, CA 91325 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Grounding or Bonding | 10/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 10/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/25/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/31/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 10/31/2022 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 11/15/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | JOHN COLEMAN |
| Special/Order Compliance | 12/16/2022 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 1/4/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 1/20/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 1/20/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 1/20/2023 | Approved | KIRK SANDERS |
| Wood Frame | 1/20/2023 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 1/25/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 1/27/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 1/27/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 1/27/2023 | Approved | KIRK SANDERS |
| Insulation | 2/7/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/7/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 2/13/2023 | Approved | KIRK SANDERS |
| Shower Pan | 3/7/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/10/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 4/13/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| Grounding or Bonding | 7/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 9/11/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 9/11/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | JUAN VALENZUELA |
| Service/Power Release | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| Smoke Detectors | 9/11/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 9/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 9/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 9/19/2023 | Approved | KIRK SANDERS |
| Final | 9/28/2023 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 9/28/2023 | Approved | KIRK SANDERS |