469 N ORLANDO AVE 90048

Certificate Information: 469 N ORLANDO AVE 90048

Application / Permit
21010-20000-00542
Plan Check / Job No.
B21VN01288
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 19'-5" X 19'-5" DETACHED 2-CAR GARAGE WITH ATTCHED 19'-6" X 8' TRELLIS. 2 OF 2. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
Issued on 1/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/20/2021 PARISA ZAHABI
Corrections Issued 2/20/2021 PARISA ZAHABI
Quality Review Completed 2/22/2021 OMID HEDAYAT
Applicant returned to address corrections 10/14/2021 PARISA ZAHABI
Applicant returned to address corrections 11/22/2021 PARISA ZAHABI
Applicant returned to address corrections 12/6/2021 PARISA ZAHABI
Applicant returned to address corrections 12/13/2021 PARISA ZAHABI
Plan Check Approved 12/13/2021 PARISA ZAHABI
Building Plans Picked Up 12/14/2021 APPLICANT
Issued 1/10/2022 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 8/3/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/10/2021 RENZ SORIANO
Low Impact Development Cleared 9/28/2021 TA ANH
Roof/Waste drainage to street Cleared 11/8/2021 JEANETTE VONG

Contact Information

Architect Jazayeri,, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Current Trend Contractors Inc; Lic. No.: 476743-B 28366 AGOURA ROAD      AGOURA HILLS, CA 91301
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/17/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved LILIANA PORTILLO
METHANE-Rough 7/17/2023 Approved LILIANA PORTILLO
Green Building Rough 8/17/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/17/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 1/24/2025 Approved JOSE MACIAS
Final 1/24/2025 Not Ready for Inspection JOSE MACIAS
Footing/Foundation/Slab 1/24/2025 Approved JOSE MACIAS
Green Building Final 1/24/2025 Approved JOSE MACIAS
METHANE-Barrier 1/24/2025 Approved JOSE MACIAS
METHANE-Subgrade 1/24/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved JOSE MACIAS
Service/Power Release 1/24/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 1/24/2025 Approved JOSE MACIAS
ELECTRICAL-Final 4/9/2025 Approved JOSE MACIAS
HVAC-Final 4/9/2025 Approved JOSE MACIAS
PLUMBING-Final 4/9/2025 Approved JOSE MACIAS
Final 5/27/2025 Not Ready for Inspection JOSE MACIAS
Service/Power Release 5/27/2025 Approved JOSE MACIAS