469 N ORLANDO AVE 90048
Certificate Information: 469 N ORLANDO AVE 90048
- Application / Permit
- 21010-20000-00541
- Plan Check / Job No.
- B21VN01288
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 54'-3 1/2" X 30'-4 1/2" IRREGULAR SHAPE 2-STORY SINGLE DAMILY DWELLING OVER HABITABLE BASEMENT - 1 OF 2. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 6/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2021 | PARISA ZAHABI |
| Corrections Issued | 2/20/2021 | PARISA ZAHABI |
| Quality Review Completed | 2/22/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/14/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 11/22/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 12/6/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 12/13/2021 | PARISA ZAHABI |
| Plan Check Approved | 12/13/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 12/14/2021 | APPLICANT |
| Issued | 1/11/2022 | APPLICANT |
| CofO in Progress | 6/6/2025 | JOSE MACIAS |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
| CofO Issued | 6/14/2025 | DEROLD HAUFF |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 6/26/2021 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/10/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 9/28/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | JEANETTE VONG |
Contact Information
| Architect | Jazayeri,, Siavash; Lic. No.: C22240 | 20230 WELLS DR WOODLAND HILLS, CA 91364 |
| Contractor | Current Trend Contractors Inc; Lic. No.: 476743-B | 28366 AGOURA ROAD AGOURA HILLS, CA 91301 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 1/18/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 1/18/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 1/20/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/19/2022 | Partial Inspection | JOSEPH MCGARRY |
| METHANE-Barrier | 7/19/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 7/19/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/19/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 8/4/2022 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/4/2022 | Partial Approval | MICHAEL LEWIS |
| Deputy Shotcrete | 8/12/2022 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/15/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 10/14/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/30/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 6/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 6/30/2023 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 7/6/2023 | Conditional Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/17/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/17/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 7/17/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 7/27/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 7/27/2023 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/2/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 8/2/2023 | Conditional Approval | LILIANA PORTILLO |
| Shower Pan | 8/2/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/10/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/17/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/17/2023 | Approved | LILIANA PORTILLO |
| METHANE-Rough | 8/17/2023 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/17/2023 | Approved | LILIANA PORTILLO |
| Insulation | 8/22/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 8/28/2023 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 9/7/2023 | Approved | LILIANA PORTILLO |
| Insulation | 9/7/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/30/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/24/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 10/24/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 10/24/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 11/21/2024 | Approved | JOSE MACIAS |
| Final | 11/21/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 11/21/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 12/19/2024 | Approved | ENRIQUE MIRELES |
| Final | 12/19/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/19/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/19/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 12/19/2024 | Approved | ENRIQUE MIRELES |
| Final | 1/24/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 1/24/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 2/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 2/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 5/9/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 5/9/2025 | Approved | WAYNE REGESTER |
| Final | 5/22/2025 | OK to Issue CofO | JOSE MACIAS |