469 N ORLANDO AVE 90048

Certificate Information: 469 N ORLANDO AVE 90048

Application / Permit
21010-20000-00541
Plan Check / Job No.
B21VN01288
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 54'-3 1/2" X 30'-4 1/2" IRREGULAR SHAPE 2-STORY SINGLE DAMILY DWELLING OVER HABITABLE BASEMENT - 1 OF 2. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 6/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/20/2021 PARISA ZAHABI
Corrections Issued 2/20/2021 PARISA ZAHABI
Quality Review Completed 2/22/2021 OMID HEDAYAT
Applicant returned to address corrections 10/14/2021 PARISA ZAHABI
Applicant returned to address corrections 11/22/2021 PARISA ZAHABI
Applicant returned to address corrections 12/6/2021 PARISA ZAHABI
Applicant returned to address corrections 12/13/2021 PARISA ZAHABI
Plan Check Approved 12/13/2021 PARISA ZAHABI
Building Plans Picked Up 12/14/2021 APPLICANT
Issued 1/11/2022 APPLICANT
CofO in Progress 6/6/2025 JOSE MACIAS
Permit Finaled 6/14/2025 DEROLD HAUFF
CofO Issued 6/14/2025 DEROLD HAUFF
Permit Finaled 6/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/11/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/26/2021 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 9/10/2021 RENZ SORIANO
Sewer availability Cleared 9/10/2021 RENZ SORIANO
Low Impact Development Cleared 9/28/2021 TA ANH
Roof/Waste drainage to street Cleared 11/8/2021 JEANETTE VONG

Contact Information

Architect Jazayeri,, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Current Trend Contractors Inc; Lic. No.: 476743-B 28366 AGOURA ROAD      AGOURA HILLS, CA 91301
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/18/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 1/18/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 1/20/2022 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/19/2022 Partial Inspection JOSEPH MCGARRY
METHANE-Barrier 7/19/2022 Approved JOSEPH MCGARRY
METHANE-Subgrade 7/19/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 7/19/2022 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 8/4/2022 Conditional Approval RYAN SALAZAR
Footing/Foundation/Slab 8/4/2022 Partial Approval MICHAEL LEWIS
Deputy Shotcrete 8/12/2022 Conditional Approval MICHAEL LEWIS
Footing/Foundation/Slab 9/15/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Corrections Issued MICHAEL LEWIS
Deputy Wood Construction 10/14/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Rough 6/30/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 6/30/2023 Corrections Issued LILIANA PORTILLO
Sewer 6/30/2023 Approved LILIANA PORTILLO
Deputy Wood Construction 7/6/2023 Conditional Approval RUBEN SALAS
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 7/17/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 7/17/2023 Approved LILIANA PORTILLO
Underground Mechanical 7/17/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 7/27/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 7/27/2023 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 8/2/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/2/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 8/2/2023 Conditional Approval LILIANA PORTILLO
Shower Pan 8/2/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 8/10/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/17/2023 Approved LILIANA PORTILLO
Green Building Rough 8/17/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/17/2023 Approved LILIANA PORTILLO
METHANE-Rough 8/17/2023 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 8/17/2023 Approved LILIANA PORTILLO
Insulation 8/22/2023 Partial Approval LILIANA PORTILLO
Insulation 8/28/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 9/7/2023 Approved LILIANA PORTILLO
Insulation 9/7/2023 Approved LILIANA PORTILLO
Underground Mechanical 1/30/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/24/2024 Corrections Issued JOSE MACIAS
Gas Test 10/24/2024 Approved JOSE MACIAS
PLUMBING-Final 10/24/2024 Approved JOSE MACIAS
ELECTRICAL-Final 11/21/2024 Approved JOSE MACIAS
Final 11/21/2024 Corrections Issued JOSE MACIAS
HVAC-Final 11/21/2024 Approved JOSE MACIAS
ELECTRICAL-Final 12/19/2024 Approved ENRIQUE MIRELES
Final 12/19/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/19/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 12/19/2024 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 12/19/2024 Approved ENRIQUE MIRELES
Final 1/24/2025 Corrections Issued JOSE MACIAS
Service/Power Release 1/24/2025 Not Ready for Inspection JOSE MACIAS
Final 2/5/2025 Not Ready for Inspection JOSE MACIAS
Service/Power Release 2/5/2025 Not Ready for Inspection JOSE MACIAS
Final 5/9/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 5/9/2025 Approved WAYNE REGESTER
Final 5/22/2025 OK to Issue CofO JOSE MACIAS