NEW IRREGULAR SHAPED, 95'-0" X 77'-9" 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND ATTACHED TRELLIS. NFPA 13D FIRE SPRIKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 1/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 ALYSSA N NARCISO
Corrections Issued 3/3/2021 ALYSSA N NARCISO
Quality Review Completed 3/10/2021 STEVEN KIM
Applicant returned to address corrections 1/26/2022 COLIN LOREDO
Applicant returned to address corrections 2/18/2022 COLIN LOREDO
Applicant returned to address corrections 2/25/2022 COLIN LOREDO
Plan Check Approved 2/25/2022 COLIN LOREDO
Issued 6/14/2022 APPLICANT
CofO in Progress 1/2/2025 JEFFREY HARTLINE
No Progress 1/2/2025 SEAN WIRCH
CofO in Progress 1/2/2025 SEAN WIRCH
CofO Issued 1/8/2025 JOHN JANSON
Permit Finaled 1/8/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/9/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/14/2021 LEE GUILBEAUX
Sewer availability Cleared 6/14/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/30/2021 MATTHEW CRAIG
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Permit Cleared 10/25/2021 JOHN LIN
Low Impact Development Cleared 12/6/2021 TA ANH
Roof/Waste drainage to street Cleared 12/7/2021 JOHN LIN
Miscellaneous Cleared 12/15/2021 KENTON TRINH
GPI Written Notices Cleared 1/26/2022 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 1/26/2022 ALYSSA N NARCISO

Contact Information

Architect Azadi,, Bijan; Lic. No.: C18972 2825 PLAZA DEL AMO # 179      TORRANCE, CA 90503
Contractor A T H Construction; Lic. No.: 691539-B 18160 CHASE STREET      NORTHRIDGE, CA 91325
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2022 Corrections Issued SEAN HAUPT
Underground Mechanical 7/8/2022 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/11/2022 Not Ready for Inspection ROBERT GOLD
Excavation/Setback/Form/Re-Bar 7/19/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 7/20/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/1/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Corrections Issued SEAN HAUPT
Green Building Rough 12/27/2022 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 12/27/2022 Not Ready for Inspection SEAN HAUPT
Deputy Wood Construction 1/25/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved DAVID SANDOVAL
PLUMBING-Rough 3/3/2023 Partial Approval VINCENT HANLEY
Special/Order Compliance 3/3/2023 Partial Inspection JESUS PINEDA
HVAC-Rough 3/10/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 3/13/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/21/2023 Approved VINCENT HANLEY
HVAC-Rough 4/21/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/24/2023 Approved VINCENT HANLEY
Green Building Rough 4/24/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/24/2023 Approved VINCENT HANLEY
Insulation 5/1/2023 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 5/1/2023 Corrections Issued VINCENT HANLEY
Shower Pan 5/1/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/2/2023 Partial Approval VINCENT HANLEY
Drywall Nailing 5/15/2023 Approved SEAN WIRCH
Interior/Exterior Lathing 6/14/2023 Approved VINCENT HANLEY
PLUMBING-Rough 2/7/2024 Partial Approval VINCENT HANLEY
PLUMBING-Rough 7/2/2024 Approved JON MCHUGH
ELECTRICAL-Final 8/23/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 8/23/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 8/27/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 9/23/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 10/9/2024 Approved THOMAS FINNILA
PLUMBING-Final 10/9/2024 Approved THOMAS FINNILA
Green Building Final 12/24/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 12/24/2024 Approved GEVORK IPCHYAN
Final 12/30/2024 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 12/30/2024 Approved JEFFREY HARTLINE