123 N LA ALAMEDA AVE 90732
Certificate Information: 123 N LA ALAMEDA AVE 90732
- Application / Permit
- 21010-20000-00503
- Plan Check / Job No.
- B21VN01215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 800 SQ. FT. STATE APPROVED MANUFACTURED ACCESSORY DWELLING UNIT WITH STATE APPROVED FOUNDATION SYSTEM
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 7/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SHAHEN AKELYAN |
| Corrections Issued | 3/4/2021 | SHAHEN AKELYAN |
| Applicant returned to address corrections | 6/3/2021 | OMAR GARNICA |
| Building Plans Picked Up | 6/22/2021 | APPLICANT |
| Applicant returned to address corrections | 8/13/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 8/19/2021 | LAWRENCE QUIRANTE |
| Issued | 8/20/2021 | APPLICANT |
| CofO in Progress | 7/18/2022 | ANSON MAGLASANG |
| Permit Finaled | 7/19/2022 | DEROLD HAUFF |
| CofO Issued | 7/19/2022 | DEROLD HAUFF |
| Permit Finaled | 7/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2021 | YEGANEH SADEGHI |
| Miscellaneous | Cleared | 3/24/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | CHINH DINH |
| Sewer availability | Cleared | 3/30/2021 | CHINH DINH |
| Grading Pre-Inspection | Cleared | 4/12/2021 | BRIAN MILLER |
| Hold | Cleared | 6/7/2021 | OMAR GARNICA |
| GPI Written Notices | Cleared | 7/7/2021 | SHAHEN AKELYAN |
| Hold | Cleared | 7/7/2021 | SHAHEN AKELYAN |
| Low Impact Development | Cleared | 7/13/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CHINH DINH |
Contact Information
| Contractor | Dba Bcc Manufactured Housing; Lic. No.: 1058049-C47 | 1930 W SAN MARCOS BLVD SPC 200 SAN MARCOS, CA 92078 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/21/2021 | No Access for Inspection | ANSON MAGLASANG |
| Green Building Rough | 12/21/2021 | No Access for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 12/21/2021 | No Access for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 12/21/2021 | No Access for Inspection | ANSON MAGLASANG |
| Underground Mechanical | 12/22/2021 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 2/17/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/8/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 3/8/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 3/8/2022 | Approved | JOHN KLARIN |
| Final | 3/29/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/29/2022 | Approved | ANSON MAGLASANG |
| Green Building Final | 3/29/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| Service/Power Release | 3/29/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 3/29/2022 | Approved | ANSON MAGLASANG |
| Final | 7/12/2022 | Corrections Issued | ANSON MAGLASANG |
| Service/Power Release | 7/12/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 7/18/2022 | OK to Issue CofO | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 7/18/2022 | Approved | ANSON MAGLASANG |