2816 3/4 W JEFFERSON BLVD 90018

Certificate Information: 2816 3/4 W JEFFERSON BLVD 90018

Application / Permit
21010-20000-00492
Plan Check / Job No.
B21VN01198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1072 SQFT 2-STORY ADU (32'-0" x 17'-8") PER LAMC 12.22 A. 33(c) AND (d)
Permit Issued
Issued on 5/17/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 PETER MOSESIAN
Corrections Issued 2/19/2021 PETER MOSESIAN
Quality Review Completed 3/8/2021 OMID HEDAYAT
Building Plans Picked Up 3/11/2021 APPLICANT
Plan Check Approved 5/2/2022 PETER MOSESIAN
Issued 5/17/2022 APPLICANT
CofO in Progress 8/21/2024 JUSTIN HAWLEY
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/12/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/12/2021 JEANIE LAM
Sewer availability Cleared 3/12/2021 JEANIE LAM
ZI Cleared 7/15/2021 GISELLE CORELLA
Hydrant and Access approval Cleared 8/13/2021 GILBERT URREA
Low Impact Development Cleared 3/24/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/30/2022 AMAAN MALIK
Community Plan Implem. Overlay Cleared 4/14/2022 KYLE WINSTON
ZI Cleared 4/14/2022 KYLE WINSTON

Contact Information

Architect Nigosian,, Michael Nickolas; Lic. No.: C35308 75-572 PAINTED DESERT DRIVE      INDIAN WELLS, CA 92210
Contractor Da Only Inc; Lic. No.: 1073836-B 9320 S LA CIENEGA BLVD      INGLEWOOD, CA 90301
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/9/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/15/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 11/21/2022 Partial Approval STUART CHAPMAN
Green Building Rough 11/21/2022 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 11/21/2022 Not Ready for Inspection STUART CHAPMAN
Wood Frame 11/21/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 12/9/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 12/9/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 12/9/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 12/23/2022 Partial Approval CALEB MEISTER
Shower Pan 12/23/2022 Approved CALEB MEISTER
Insulation 1/3/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 1/3/2023 Not Ready for Inspection MICHAEL LEWIS
Drywall Nailing 1/24/2023 Approved CALEB MEISTER
Green Building Rough 1/24/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 2/7/2024 Approved JUSTIN HAWLEY
Final 2/7/2024 Corrections Issued JUSTIN HAWLEY
HVAC-Rough 2/7/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/7/2024 Approved JUSTIN HAWLEY
Service/Power Release 2/7/2024 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 7/17/2024 Conditional Approval DAVID FEILER
Final 7/17/2024 Corrections Issued DAVID FEILER
Green Building Final 7/17/2024 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/17/2024 SGSOV Not Required DAVID FEILER
Service/Power Release 7/17/2024 Not Required DAVID FEILER
Smoke Detectors 7/17/2024 Approved DAVID FEILER
Verify Sprinkler Sign Off 7/17/2024 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/15/2024 Approved JUSTIN HAWLEY
Final 8/15/2024 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Final 8/21/2024 Approved JUSTIN HAWLEY
Final 8/21/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 8/21/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 8/21/2024 Approved JUSTIN HAWLEY