7620-7626 N BALBOA BLVD 91406
Certificate Information: 7620-7626 N BALBOA BLVD 91406
- Application / Permit
- 21010-20000-00488
- Plan Check / Job No.
- B21VN01167
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- (N) 1-STORY AUTO DISMANTLING & STORAGE BLDG
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 2/19/2021 | APPLICANT |
| Corrections Issued | 2/23/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/23/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/26/2021 | APPLICANT |
| Applicant returned to address corrections | 5/6/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/13/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/26/2022 | NILOOFAR MEHRAIN |
| Issued | 8/17/2022 | APPLICANT |
| CofO in Progress | 1/4/2024 | JEFFREY FULTON |
| CofO Issued | 1/26/2024 | JEFFREY DURAN |
| Permit Finaled | 1/26/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2021 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 3/9/2021 | JOHN TRIANTAFYLLOS |
| Automotive Use | Cleared | 3/10/2021 | LAUREN PADICK |
| Green Code | Cleared | 3/10/2021 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | JOHN TRIANTAFYLLOS |
| Automotive Use | Cleared | 3/17/2021 | LAUREN PADICK |
| Prkng lot landscape/Water mgmt | Cleared | 3/17/2021 | LAUREN PADICK |
| DAS Clearance | Cleared | 3/24/2021 | NILOOFAR MEHRAIN |
| Sewer availability | Cleared | 4/22/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 5/22/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/1/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 4/22/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91206 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/23/2022 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 8/25/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Other (see comments) | 8/31/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Masonry | 8/31/2022 | Conditional Approval | JEFFREY FULTON |
| Masonry Wall/Backfill | 8/31/2022 | Corrections Issued | JEFFREY FULTON |
| Deputy Other (see comments) | 9/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 9/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Other (see comments) | 9/2/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 9/2/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Other (see comments) | 9/7/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Masonry | 9/7/2022 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 10/3/2022 | Partial Inspection | JEFFREY FULTON |
| Masonry Wall/Backfill | 10/11/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Other (see comments) | 10/14/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 10/14/2022 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 10/17/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Other (see comments) | 10/20/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Masonry | 10/20/2022 | Conditional Approval | JEFFREY FULTON |
| Masonry Wall/Backfill | 11/14/2022 | Corrections Issued | DANNY RODRIGUEZ |
| Deputy Other (see comments) | 11/15/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 11/15/2022 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 11/16/2022 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | No Access for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Corrections Issued | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 12/22/2022 | Partial Inspection | BRIAN KELLY |
| Deputy Drilled-In Anchors | 12/23/2022 | Conditional Approval | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 6/22/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | JEFFREY FULTON |
| Wood Frame | 6/28/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 7/7/2023 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 7/27/2023 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 8/8/2023 | Approved | JEFFREY FULTON |
| Wood Frame | 8/8/2023 | Approved | JEFFREY FULTON |
| Pre-Inspection | 10/17/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Inspection | 11/21/2023 | Not Ready for Inspection | JOHN KITCKO |
| Final | 12/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 12/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 12/7/2023 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV No Gas | JEFFREY FULTON |
| Smoke Detectors | 12/7/2023 | Approved | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 12/7/2023 | Approved | JEFFREY FULTON |
| Green Building Final | 12/11/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 12/18/2023 | OK to Issue CofO | JEFFREY FULTON |
| Green Building Final | 12/18/2023 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/18/2023 | Approved | JEFFREY FULTON |
| Deputy Steel/Welding | 12/21/2023 | Conditional Approval | JEFFREY FULTON |