13201 W HANEY PL 90049
Certificate Information: 13201 W HANEY PL 90049
- Application / Permit
- 21010-20000-00476
- Plan Check / Job No.
- B21VN01122
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 64' X 71'6" 2-STORY SFD WITH ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | RARES BODEA |
| Corrections Issued | 2/6/2021 | RARES BODEA |
| Quality Review Completed | 2/11/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/16/2021 | APPLICANT |
| Applicant returned to address corrections | 4/16/2021 | RARES BODEA |
| Plan Check Approved | 5/10/2021 | RARES BODEA |
| Issued | 5/10/2021 | APPLICANT |
| CofO in Progress | 6/8/2022 | JUAN VALENZUELA |
| Permit Finaled | 6/15/2022 | DANIEL ORRANTE |
| CofO Issued | 6/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/16/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 2/26/2021 | RAYMOND MUGAMBWA |
| Trees in Parkway | Cleared | 3/3/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 3/18/2021 | KURT CORRAL |
| Address approval | Cleared | 3/24/2021 | RAYMOND MUGAMBWA |
| Permit | Cleared | 3/24/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 3/31/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 4/6/2021 | RAYMOND MUGAMBWA |
| GPI Written Notices | Cleared | 5/3/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 5/3/2021 | RARES BODEA |
Contact Information
| Contractor | E T Development Inc; Lic. No.: 994749-B | 7256 BELLAIRE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/27/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Conditional Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/14/2021 | Conditional Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/30/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 8/30/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 8/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/1/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 9/1/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/9/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/9/2021 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/9/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 9/17/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 9/17/2021 | Approved | JUAN VALENZUELA |
| Insulation | 9/24/2021 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 10/4/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 5/16/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 5/16/2022 | Approved | JOHN KIDWELL |
| Final | 5/25/2022 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/25/2022 | Approved | JOHN KIDWELL |
| Green Building Final | 5/25/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 5/25/2022 | Approved | JOHN KIDWELL |
| Smoke Detectors | 5/25/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 6/7/2022 | Approved | JUAN VALENZUELA |
| Final | 6/7/2022 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 6/7/2022 | Approved | JUAN VALENZUELA |