19253 W BERCLAIR LANE 91356

Certificate Information: 19253 W BERCLAIR LANE 91356

Application / Permit
21010-20000-00469
Plan Check / Job No.
B21VN01086
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12'-6" X 18'-4" DETACHED RECREATION ROOM W/ IRREGULAR 23'-6" X 30'-4" TRELLIS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 10/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 JENNIFER LEE
Corrections Issued 2/19/2021 JENNIFER LEE
Plan Check Approved 6/16/2021 JENNIFER LEE
Issued 6/16/2021 APPLICANT
Building Plans Picked Up 6/16/2021 APPLICANT
CofO in Progress 4/18/2023 DAVID SANDOVAL
CofO Issued 10/17/2023 JOHN JANSON
Permit Finaled 10/17/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/26/2021 ADRIAN CASTRO
Sewer availability Cleared 3/26/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/31/2021 ADRIAN CASTRO
ZA Case Cleared 4/26/2021 TERRI OSBORNE
Grading Pre-Inspection Cleared 6/1/2021 KIRK LINKLATER
GPI Written Notices Cleared 6/14/2021 JENNIFER LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/20/2023 Not Ready for Inspection DAVID SANDOVAL
Sewer 1/20/2023 Not Ready for Inspection DAVID SANDOVAL
Underground Mechanical 1/20/2023 Partial Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved DAVID SANDOVAL
Footing/Foundation/Slab 1/25/2023 Not Ready for Inspection DAVID SANDOVAL
Deputy Steel/Welding 2/10/2023 Partial Approval SEAN WIRCH
Deputy Wood Construction 2/14/2023 Conditional Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Approved JON MCHUGH
PLUMBING-Rough 2/17/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 2/23/2023 Approved DAVID SANDOVAL
ELECTRICAL-Rough 2/23/2023 Approved DAVID SANDOVAL
Green Building Rough 2/23/2023 Approved DAVID SANDOVAL
Interior/Exterior Lathing 2/23/2023 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 2/23/2023 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 2/23/2023 Approved DAVID SANDOVAL
Insulation 3/1/2023 Approved DAVID SANDOVAL
Special/Order Compliance 3/1/2023 Partial Inspection JUSTIN HAWLEY
Drywall Nailing 3/6/2023 Approved DAVID SANDOVAL
Final 3/28/2023 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 3/28/2023 Approved DAVID SANDOVAL
Green Building Final 3/28/2023 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved DAVID SANDOVAL
Service/Power Release 3/28/2023 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 3/28/2023 Approved DAVID SANDOVAL
Verify Rec and Parks Fee Memo 3/28/2023 Approved DAVID SANDOVAL
Final 4/6/2023 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Final 4/6/2023 Approved DAVID SANDOVAL
PLUMBING-Final 4/6/2023 Approved DAVID SANDOVAL
ELECTRICAL-Final 4/17/2023 Approved DAVID SANDOVAL
Final 4/17/2023 OK to Issue CofO DAVID SANDOVAL