13715 N ELDRIDGE AVE 91342
Certificate Information: 13715 N ELDRIDGE AVE 91342
- Application / Permit
- 21010-20000-00467
- Plan Check / Job No.
- B21VN01077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- PROPOSED NEW DETACHED 20'X40' GARAGE W/ATT 11'X40' CARPORT PER ENGR DESIGN. SEE COMMENTS.
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 2/14/2021 | HAYATO TSUCHIYA |
| Issued | 3/3/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 3/4/2026 | KEVIN BERBERYAN |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/10/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/26/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/28/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/28/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/3/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/22/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/22/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 9/22/2025 | Not Required | KEVIN BERBERYAN |
| Smoke Detectors | 9/22/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/3/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 3/3/2026 | Approved | KEVIN BERBERYAN |