4018 N MARY ELLEN AVE 91604
Certificate Information: 4018 N MARY ELLEN AVE 91604
- Application / Permit
- 21010-20000-00443
- Plan Check / Job No.
- B21VN01025
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 41'-2" X 63' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SELLA BENYAMIN |
| Corrections Issued | 2/2/2021 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/4/2021 | APPLICANT |
| Plan Check Approved | 6/3/2021 | SELLA BENYAMIN |
| Issued | 7/16/2021 | APPLICANT |
| CofO in Progress | 6/6/2023 | CHRISTOPHE COCHRAN |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
| CofO Issued | 6/8/2023 | MICHAEL SMITH |
| Permit Finaled | 6/8/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 2/24/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| Trees in Parkway | Cleared | 4/8/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/15/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 6/3/2021 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 6/3/2021 | SELLA BENYAMIN |
| Roof/Waste drainage to street | Cleared | 6/10/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 9/13/2021 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/24/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | WILLIAM WREN |
| Wood Frame | 10/12/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 12/30/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/30/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/6/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 1/6/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/6/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/19/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/26/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/1/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 2/3/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 3/16/2022 | Corrections Issued | ARAM AVEDISIAN |
| Shower Pan | 3/16/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 3/21/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 3/22/2022 | Approved | CALEB MEISTER |
| Gas Test | 3/22/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/29/2022 | Approved | CALEB MEISTER |
| Sewer | 9/1/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 4/24/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 4/24/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/24/2023 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/24/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/2/2023 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 6/2/2023 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/2/2023 | Approved | CHRISTOPHE COCHRAN |