19122 W HALSTED ST 91324
Certificate Information: 19122 W HALSTED ST 91324
- Application / Permit
- 21010-20000-00419
- Plan Check / Job No.
- B21VN00990
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 18'-11" X 27' DETACHED GARAGE W/ STORAGE AND BATHROOM (EXTERIOR ACCESS ONLY). ALL WORK PER ENGINEERIGNG.
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/14/2021 | RAPHAEL ROSAS |
| Issued | 6/18/2021 | APPLICANT |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| CofO in Progress | 7/19/2024 | DAVID SCANTLIN |
| CofO in Progress | 7/22/2024 | DAVID SCANTLIN |
| CofO in Progress | 9/9/2024 | DAVID SCANTLIN |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
| CofO Issued | 9/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 5/21/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/21/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/16/2021 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/29/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 7/9/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/3/2021 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/15/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 9/15/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/23/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 9/23/2021 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 10/27/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 3/19/2024 | Partial Approval | KRISTEN CAUSEY |
| Sewer | 3/21/2024 | Approved | KRISTEN CAUSEY |
| Final | 5/3/2024 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/3/2024 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/3/2024 | Approved | DAVID SCANTLIN |
| Final | 7/19/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 7/29/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 9/9/2024 | OK to Issue CofO | DAVID SCANTLIN |