22122 W VICTORY BLVD #I 91367
Certificate Information: 22122 W VICTORY BLVD #I 91367
- Application / Permit
- 21010-20000-00380
- Plan Check / Job No.
- B21VN00893
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (22) Storage Building
- Work Description
- (N) 1-STORY TYPE V-A MAINTENANCE STORAGE BUILDING (67' X 30') ACCESSORY TO (E) APT BLDGS
- Permit Issued
- Issued on 10/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 3/10/2021 | APPLICANT |
| Green Plans Picked Up | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/18/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/23/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/22/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/4/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/22/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/22/2023 | NILOOFAR MEHRAIN |
| Issued | 10/13/2023 | APPLICANT |
| CofO in Progress | 11/21/2024 | ROBERT DAVIS |
| Permit Finaled | 12/13/2024 | RICKEY JACKSON |
| CofO Issued | 12/13/2024 | RICKEY JACKSON |
| Permit Finaled | 12/13/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Green Code | Cleared | 6/16/2021 | MICHAEL AYERS |
| DAS Clearance | Cleared | 6/17/2021 | NORLITO MEDRANO |
| Hydrant and Access approval | Cleared | 7/22/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 7/28/2021 | DANG NGUYEN |
| ZA Case | Cleared | 7/28/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | THAN WIN |
| Address approval | Cleared | 2/22/2022 | CARLOS AGUILERA |
| Highway dedication | Cleared | 2/22/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/14/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/26/2023 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/31/2023 | LEE GUILBEAUX |
Contact Information
| Architect | Dorman,, Christopher J; Lic. No.: C28300 | 229 FLAMINGO ROAD MILL VALLEY, CA 94941 |
| Contractor | Grundco; Lic. No.: 1016287-B | 24372 VANOWEN ST STE 205 WEST HILLS, CA 91307 |
| Engineer | Billante,, Ryan Dylan; Lic. No.: C58814 | 4377 SECOND ST PLEASANTON, CA 94566 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/11/2024 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/11/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 1/16/2024 | Corrections Issued | JEFFREY FULTON |
| Footing/Foundation/Slab | 5/8/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 5/13/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 5/23/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 5/23/2024 | Conditional Approval | STEVEN LEVITT |
| Reinforced Concrete Frame | 5/23/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 5/24/2024 | Conditional Approval | STEVEN LEVITT |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Approved | STEVEN LEVITT |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 8/2/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Verify Sprinkler Sign Off | 8/2/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Wood Frame | 8/5/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 8/6/2024 | Approved | ROBERT DAVIS |
| Green Building Rough | 8/13/2024 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 8/13/2024 | Approved | GREGORY POMISH |
| Wood Frame | 8/13/2024 | Approved | GREGORY POMISH |
| Insulation | 8/15/2024 | Not Ready for Inspection | GREGORY POMISH |
| Insulation | 8/16/2024 | Approved | GREGORY POMISH |
| Drywall Nailing | 8/19/2024 | No Access for Inspection | ROBERT DAVIS |
| Drywall Nailing | 8/22/2024 | Approved | ROBERT DAVIS |
| Final | 10/11/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 10/11/2024 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 10/11/2024 | No Access for Inspection | ROBERT DAVIS |
| Final | 11/19/2024 | Partial Inspection | BRIAN KELLY |
| Smoke Detectors | 11/19/2024 | Approved | BRIAN KELLY |
| Final | 11/21/2024 | OK to Issue CofO | ROBERT DAVIS |