4534 N TOBIAS AVE 91403

Certificate Information: 4534 N TOBIAS AVE 91403

Application / Permit
21010-20000-00361
Plan Check / Job No.
B21VN00811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12'-9" X 18' DETACHED REC ROOM WITH HALF BATHROOM AND SHOWER WITH EXTERIOR ACCESS ONLY
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 SELLA BENYAMIN
Corrections Issued 2/4/2021 SELLA BENYAMIN
Quality Review Completed 2/4/2021 STEVEN KIM
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 10/13/2021 SELLA BENYAMIN
Issued 10/20/2021 APPLICANT
CofO in Progress 10/20/2022 MISAEL ESPARZA
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2021 GABRIEL ROBLES
Construction near power lines Cleared 8/21/2021 RIDWAN HARDY
Low Impact Development Cleared 9/14/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/5/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/29/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 10/29/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 11/2/2021 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 11/2/2021 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 11/4/2021 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 11/8/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/12/2022 Partial Approval ASHLEY THOMPSON
HVAC-Rough 1/26/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/26/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/18/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/18/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 2/18/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/18/2022 Approved MISAEL ESPARZA
HVAC-Rough 2/24/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 2/24/2022 Approved MISAEL ESPARZA
Wood Frame 2/24/2022 Approved MISAEL ESPARZA
Drywall Nailing 3/7/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/7/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/23/2022 Approved MISAEL ESPARZA
Final 9/23/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/23/2022 Approved MISAEL ESPARZA
Green Building Final 9/23/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/23/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/23/2022 Approved MISAEL ESPARZA
PLUMBING-Final 9/29/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/3/2022 Approved MISAEL ESPARZA
HVAC-Final 10/3/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/6/2022 Approved MISAEL ESPARZA
Final 10/19/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 10/19/2022 Approved MISAEL ESPARZA
Service/Power Release 10/19/2022 Approved MISAEL ESPARZA