4534 N TOBIAS AVE 91403

Certificate Information: 4534 N TOBIAS AVE 91403

Application / Permit
21010-20000-00360
Plan Check / Job No.
B21VN00811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 60' X 37' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 SELLA BENYAMIN
Corrections Issued 2/4/2021 SELLA BENYAMIN
Quality Review Completed 2/4/2021 STEVEN KIM
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 10/13/2021 SELLA BENYAMIN
Issued 10/20/2021 APPLICANT
CofO in Progress 10/20/2022 MISAEL ESPARZA
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/21/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 6/21/2021 GABRIEL ROBLES
Permit Cleared 6/21/2021 GABRIEL ROBLES
Sewer availability Cleared 6/21/2021 GABRIEL ROBLES
Trees in Parkway Cleared 8/11/2021 JOHN KIM
ZI Cleared 8/31/2021 MIGUEL GAMBOA
Low Impact Development Cleared 9/14/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/5/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/26/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/26/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/29/2021 Corrections Issued MARK JOHNSON
Pre-Inspection 10/29/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 11/2/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/4/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/12/2022 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/21/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 1/26/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/26/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/18/2022 Approved MISAEL ESPARZA
Green Building Rough 2/18/2022 Approved MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 2/18/2022 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/18/2022 Approved MISAEL ESPARZA
Insulation 2/24/2022 Approved MISAEL ESPARZA
Drywall Nailing 3/2/2022 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 3/7/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/7/2022 Approved MISAEL ESPARZA
Final 9/23/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/23/2022 Approved MISAEL ESPARZA
Green Building Final 9/23/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/23/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/23/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/29/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/3/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 10/3/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/6/2022 Approved MISAEL ESPARZA
Final 10/19/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 10/19/2022 Approved MISAEL ESPARZA
Service/Power Release 10/19/2022 Approved MISAEL ESPARZA
Smoke Detectors 10/19/2022 Approved MISAEL ESPARZA