2020 N STRADELLA ROAD 90077

Certificate Information: 2020 N STRADELLA ROAD 90077

Application / Permit
21010-20000-00348
Plan Check / Job No.
B21VN00747
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED (75'-9" X 87'-6"), 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE, BASEMENT, & ROOF DECK. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
CofO Issued on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 COLIN LOREDO
Corrections Issued 2/18/2021 COLIN LOREDO
Quality Review Completed 3/4/2021 OMID HEDAYAT
Building Plans Picked Up 3/5/2021 APPLICANT
Applicant returned to address corrections 3/25/2021 COLIN LOREDO
Applicant returned to address corrections 4/29/2021 COLIN LOREDO
Applicant returned to address corrections 5/25/2021 COLIN LOREDO
Applicant returned to address corrections 8/3/2021 COLIN LOREDO
Plan Check Approved 9/1/2021 COLIN LOREDO
Issued 9/2/2021 APPLICANT
CofO in Progress 11/4/2024 CHRISTOPHER WILSON
Permit Finaled 11/7/2024 RICHARD STEINBACH
CofO Issued 11/7/2024 RICHARD STEINBACH
Permit Finaled 11/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/5/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/5/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/5/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/5/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 3/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/5/2021 DINAH GARIN
Permit Cleared 3/5/2021 DINAH GARIN
Sewer availability Cleared 3/5/2021 DINAH GARIN
Hydrant and Access approval Cleared 4/29/2021 KURT CORRAL
Low Impact Development Cleared 7/2/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/21/2021 DINAH GARIN
Grading Pre-Inspection Cleared 8/3/2021 COLIN LOREDO

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Owner-Builder       ,
Engineer Masterman,, Gary Clyde; Lic. No.: GE567 1766 EAGLE RIDGE CIR      WICHITA FALLS, TX 76309
Engineer Price,, Mark E; Lic. No.: L7764 18700 WELLHAVEN STREET      CANYON COUNTRY, CA 91351
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 11/16/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/23/2021 Corrections Issued MICHAEL PELHAM
Piling/Pier/Caisson 11/23/2021 Partial Approval MICHAEL PELHAM
Deputy Grading 1/28/2022 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 1/28/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/10/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/1/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 4/19/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 4/21/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/2/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/3/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/4/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/12/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/8/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/9/2022 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/13/2022 No Access for Inspection MICHAEL PELHAM
Deputy Shotcrete 6/15/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 6/30/2022 Partial Approval CHRISTOPHER WILSON
Deputy Grading 7/11/2022 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 7/19/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/19/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/22/2022 Conditional Approval CHRISTOPHER WILSON
Wood Frame 8/16/2022 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 8/19/2022 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 9/13/2022 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 9/13/2022 Approved CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/15/2022 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/3/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 10/5/2022 Conditional Approval MICHAEL PELHAM
Drywall Nailing 10/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 2/21/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 3/24/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/26/2023 Partial Inspection CHRISTOPHER WILSON
Underground Mechanical 4/26/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/4/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 5/10/2023 Approved CHRISTOPHER WILSON
Underground Mechanical 5/15/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 6/9/2023 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 6/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 6/26/2023 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/27/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 6/27/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 6/27/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 7/31/2023 Approved CHRISTOPHER WILSON
HVAC-Rough 7/31/2023 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/9/2023 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 8/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/9/2023 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/16/2023 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 8/16/2023 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/16/2023 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/16/2023 Corrections Issued MICHAEL PELHAM
Interior/Exterior Lathing 8/18/2023 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 8/23/2023 Partial Inspection BEN MOLSTAD
Special/Order Compliance 8/23/2023 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/23/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 8/23/2023 Partial Inspection STEPHANIE SWANSON
Special/Order Compliance 8/23/2023 Partial Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/25/2023 Partial Approval CHRISTOPHER WILSON
Green Building Rough 8/25/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/6/2023 Approved CHRISTOPHER WILSON
Green Building Rough 9/6/2023 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 9/6/2023 Approved CHRISTOPHER WILSON
Special/Order Compliance 9/6/2023 Partial Inspection MICHAEL PELHAM
Drywall Nailing 9/18/2023 Approved CHRISTOPHER WILSON
Insulation 9/18/2023 Approved CHRISTOPHER WILSON
HVAC-Final 5/30/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 6/5/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 6/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 6/10/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 6/10/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 6/10/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 6/25/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 6/25/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 6/28/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 7/3/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 7/15/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 8/28/2024 Partial Approval MICHAEL PELHAM
ELECTRICAL-Final 9/23/2024 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 9/23/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 10/2/2024 Corrections Issued CHRISTOPHER WILSON
Final 10/7/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 10/7/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Not Ready CHRISTOPHER WILSON
Service/Power Release 10/7/2024 Approved CHRISTOPHER WILSON
Smoke Detectors 10/7/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/30/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Final 10/30/2024 Approved CHRISTOPHER WILSON
HVAC-Final 10/30/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 10/30/2024 Approved CHRISTOPHER WILSON
Final 11/1/2024 OK to Issue CofO CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Approved CHRISTOPHER WILSON
Service/Power Release 11/1/2024 Approved CHRISTOPHER WILSON