2020 N STRADELLA ROAD 90077
Certificate Information: 2020 N STRADELLA ROAD 90077
- Application / Permit
- 21010-20000-00348
- Plan Check / Job No.
- B21VN00747
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRREGULAR SHAPED (75'-9" X 87'-6"), 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 3-CAR GARAGE, BASEMENT, & ROOF DECK. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/2/2021
- Issuing Office
- Current Status
- CofO Issued on 11/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | COLIN LOREDO |
| Corrections Issued | 2/18/2021 | COLIN LOREDO |
| Quality Review Completed | 3/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Applicant returned to address corrections | 3/25/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 4/29/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 5/25/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 8/3/2021 | COLIN LOREDO |
| Plan Check Approved | 9/1/2021 | COLIN LOREDO |
| Issued | 9/2/2021 | APPLICANT |
| CofO in Progress | 11/4/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 11/7/2024 | RICHARD STEINBACH |
| CofO Issued | 11/7/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/7/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/5/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/5/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/5/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/5/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 3/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | DINAH GARIN |
| Permit | Cleared | 3/5/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/5/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/29/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 7/2/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/21/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 8/3/2021 | COLIN LOREDO |
Contact Information
| Architect | Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 | 17116 RAYMER STREET NORTHRIDGE, CA 91325 |
| Contractor | Owner-Builder | , |
| Engineer | Masterman,, Gary Clyde; Lic. No.: GE567 | 1766 EAGLE RIDGE CIR WICHITA FALLS, TX 76309 |
| Engineer | Price,, Mark E; Lic. No.: L7764 | 18700 WELLHAVEN STREET CANYON COUNTRY, CA 91351 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 11/16/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/23/2021 | Corrections Issued | MICHAEL PELHAM |
| Piling/Pier/Caisson | 11/23/2021 | Partial Approval | MICHAEL PELHAM |
| Deputy Grading | 1/28/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 1/28/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 4/19/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/21/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 5/2/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 5/4/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/12/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 6/8/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 6/13/2022 | No Access for Inspection | MICHAEL PELHAM |
| Deputy Shotcrete | 6/15/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/30/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Grading | 7/11/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 7/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/22/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Wood Frame | 8/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 8/19/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 9/13/2022 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/13/2022 | Approved | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 9/15/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 10/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Wood Construction | 10/5/2022 | Conditional Approval | MICHAEL PELHAM |
| Drywall Nailing | 10/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Wood Construction | 2/21/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 3/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Conditional Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/26/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Underground Mechanical | 4/26/2023 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/4/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/10/2023 | Approved | CHRISTOPHER WILSON |
| Underground Mechanical | 5/15/2023 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Wood Construction | 6/9/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Green Building Rough | 6/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 6/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/26/2023 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 6/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/31/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 7/31/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/9/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 8/9/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/16/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 8/16/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/16/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/16/2023 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 8/18/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | BEN MOLSTAD |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/25/2023 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 8/25/2023 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/6/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 9/6/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/6/2023 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 9/6/2023 | Partial Inspection | MICHAEL PELHAM |
| Drywall Nailing | 9/18/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 9/18/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 5/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 6/5/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/6/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 6/10/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 6/10/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/10/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/25/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 6/25/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/28/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 7/3/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 7/15/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 8/28/2024 | Partial Approval | MICHAEL PELHAM |
| ELECTRICAL-Final | 9/23/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 9/23/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 10/7/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 10/7/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Service/Power Release | 10/7/2024 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 10/7/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 10/30/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 10/30/2024 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 10/30/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/30/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 10/30/2024 | Approved | CHRISTOPHER WILSON |
| Final | 11/1/2024 | OK to Issue CofO | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Approved | CHRISTOPHER WILSON |
| Service/Power Release | 11/1/2024 | Approved | CHRISTOPHER WILSON |