21713 W BASSETT ST 91303
Certificate Information: 21713 W BASSETT ST 91303
- Application / Permit
- 21010-20000-00345
- Plan Check / Job No.
- B21VN00741
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42' X 28'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | PARISA ZAHABI |
| Corrections Issued | 2/14/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 6/30/2021 | PARISA ZAHABI |
| Plan Check Approved | 7/14/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Issued | 8/11/2021 | APPLICANT |
| CofO in Progress | 2/15/2023 | ALEXANDER HANDY |
| CofO Issued | 2/24/2023 | JOHN JANSON |
| Permit Finaled | 2/24/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/22/2021 | MITESH PATEL |
| Address approval | Cleared | 4/1/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/13/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/24/2021 | ADRIAN CASTRO |
| CPC | Cleared | 5/4/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 5/4/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 6/15/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 121 N VAIL AVE MONTEBELLO, CA 90640 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/10/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 12/10/2021 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 12/10/2021 | Partial Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/4/2022 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/4/2022 | Conditional Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/11/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 4/11/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 4/11/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/21/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/12/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/12/2022 | Approved | STEVEN BACK |
| Deputy Wood Construction | 5/16/2022 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | STEVEN BACK |
| Green Building Rough | 6/7/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/7/2022 | Approved | STEVEN BACK |
| Shower Pan | 6/7/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 7/5/2022 | Approved | JESUS PINEDA |
| Insulation | 7/5/2022 | Approved | JESUS PINEDA |
| Sewer | 9/14/2022 | No Access for Inspection | STEVEN BACK |
| Pre-Inspection | 9/15/2022 | Corrections Issued | STEVEN BACK |
| Sewer | 9/15/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 9/15/2022 | Approved | STEVEN BACK |
| Final | 11/2/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/2/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 11/2/2022 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 11/2/2022 | Approved | STEVEN BACK |
| Final | 1/10/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/10/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/14/2023 | Approved | ALEXANDER HANDY |
| Final | 2/14/2023 | OK to Issue CofO | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | ALEXANDER HANDY |