1171-1173 W 36TH PL 90007

Certificate Information: 1171-1173 W 36TH PL 90007

Application / Permit
21010-20000-00341
Plan Check / Job No.
B21VN00728
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 49'9-1/4" X 33' FOUR STORY DUPLEX FULLY SPRINKLERED NFPA-13R (TYPE VB CONSTRUCTION ) WITH (2) ATTACHED TWO CAR GARAGE AND ONE CAR CARPORT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 RARES BODEA
Corrections Issued 2/20/2021 RARES BODEA
Quality Review Completed 3/4/2021 STEVEN KIM
Building Plans Picked Up 3/4/2021 APPLICANT
Applicant returned to address corrections 5/24/2022 RARES BODEA
Applicant returned to address corrections 6/27/2023 RARES BODEA
Plan Check Approved 8/4/2023 RARES BODEA
Issued 8/4/2023 APPLICANT
CofO in Progress 11/19/2025 SABAS ALONSO
Permit Finaled 11/20/2025 DEROLD HAUFF
CofO Issued 11/20/2025 DEROLD HAUFF
Permit Finaled 11/20/2025 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 4/8/2021 LOUIS ORTEGA
ZA Case Cleared 4/8/2021 LOUIS ORTEGA
Address approval Cleared 5/12/2022 JEANETTE VONG
ZI Cleared 5/18/2022 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 5/31/2022 JEANETTE VONG
Sewer availability Cleared 5/31/2022 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 7/13/2022 LOUIS ORTEGA
Trees in Parkway Cleared 7/20/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 8/16/2022 JOHN CONNEALLY
Low Impact Development Cleared 8/30/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 9/1/2022 JEANETTE VONG
Highway dedication Cleared 2/6/2023 JEANETTE VONG
Permit Cleared 5/25/2023 TREVOR QUAN

Contact Information

Architect Vanos,, Vincent Jay; Lic. No.: C22269 2747 MARQUETTE DR      TOPANGA, CA 90290
Contractor B M R Enterprises; Lic. No.: 901546-B 5250 LANKERSHIM BLVD STE 500      LOS ANGELES, CA 91601
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 12/8/2023 Conditional Approval SABAS ALONSO
METHANE-Subgrade 12/8/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/18/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 2/13/2024 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 2/16/2024 Partial Approval SABAS ALONSO
METHANE-Barrier 2/20/2024 No Access for Inspection SABAS ALONSO
METHANE-Subgrade 2/20/2024 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 3/15/2024 Corrections Issued SABAS ALONSO
METHANE-Barrier 3/15/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 3/15/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 3/19/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Barrier 3/19/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 3/19/2024 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 3/20/2024 Conditional Approval SABAS ALONSO
Deputy Reinf. Concrete 3/26/2024 Conditional Approval SABAS ALONSO
METHANE-Barrier 4/2/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 4/2/2024 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 4/2/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 4/11/2024 Corrections Issued SABAS ALONSO
METHANE-Barrier 4/11/2024 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 4/12/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 4/29/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 4/30/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 5/6/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 5/10/2024 Conditional Approval DAVID FEILER
Deputy Steel/Welding 5/16/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 5/17/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 5/20/2024 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 5/21/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Not Ready for Inspection ANTHONY EGSON
Deputy Steel/Welding 5/23/2024 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 5/23/2024 Approved SABAS ALONSO
METHANE-Barrier 5/23/2024 Approved SABAS ALONSO
Underground Mechanical 5/23/2024 Partial Approval SABAS ALONSO
Deputy Steel/Welding 5/24/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 8/2/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/29/2024 No Access for Inspection SABAS ALONSO
Wood Frame 8/29/2024 No Access for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/3/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/4/2024 Corrections Issued SABAS ALONSO
Verify Sprinkler Sign Off 10/4/2024 Approved SABAS ALONSO
HVAC-Rough 10/31/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 11/1/2024 Corrections Issued JOAQUIN GREENOUGH
Insulation 11/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 11/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 11/7/2024 Approved SABAS ALONSO
Insulation 11/13/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/13/2024 Not Ready for Inspection SABAS ALONSO
Wood Frame 11/13/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/2/2024 Approved SABAS ALONSO
Green Building Rough 12/2/2024 Approved SABAS ALONSO
Insulation 12/2/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 12/2/2024 Partial Approval SABAS ALONSO
METHANE-Rough 12/2/2024 Approved SABAS ALONSO
Drywall Nailing 12/19/2024 Approved SABAS ALONSO
Underground Mechanical 5/8/2025 Partial Approval SABAS ALONSO
Sewer 5/15/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/20/2025 Partial Inspection SABAS ALONSO
Interior/Exterior Lathing 5/21/2025 Approved SABAS ALONSO
ELECTRICAL-Final 5/27/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 5/27/2025 Not Ready for Inspection BARRY HACHE
Gas Test 5/29/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 5/29/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 5/29/2025 Not Ready for Inspection WAYNE REGESTER
Gas Test 5/30/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 6/3/2025 Approved BRENDAN MORELLI
PLUMBING-Final 6/3/2025 Approved BRENDAN MORELLI
Final 6/20/2025 Corrections Issued SABAS ALONSO
Green Building Final 6/20/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 6/20/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 6/20/2025 Approved SABAS ALONSO
Service/Power Release 9/15/2025 Not Ready for Inspection SABAS ALONSO
Final 10/9/2025 Corrections Issued SABAS ALONSO
Service/Power Release 10/9/2025 Approved SABAS ALONSO
Final 11/18/2025 OK to Issue CofO SABAS ALONSO