4647 N TALOFA AVE 91602
Certificate Information: 4647 N TALOFA AVE 91602
- Application / Permit
- 21010-20000-00333
- Plan Check / Job No.
- B21VN00716
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 13' X 18' PATIO COVER
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 5/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SELLA BENYAMIN |
| Corrections Issued | 2/4/2021 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/4/2021 | APPLICANT |
| Plan Check Approved | 10/5/2021 | SELLA BENYAMIN |
| Issued | 10/6/2021 | APPLICANT |
| CofO in Progress | 5/10/2022 | ARAM AVEDISIAN |
| Permit Finaled | 5/10/2022 | MICHAEL SMITH |
| CofO Issued | 5/10/2022 | MICHAEL SMITH |
| Permit Finaled | 5/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/20/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/27/2021 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/27/2021 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/3/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 11/24/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/30/2021 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 12/3/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 12/3/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 12/16/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | ARAM AVEDISIAN |
| Final | 4/25/2022 | Corrections Issued | ARAM AVEDISIAN |
| MERV13>=Final | 4/25/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 4/25/2022 | Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 4/25/2022 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 4/28/2022 | Approved | RICHARD DOCKUS |
| Final | 5/9/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 5/10/2022 | OK to Issue CofO | ARAM AVEDISIAN |