18944 W STRATHERN ST 91335

Certificate Information: 18944 W STRATHERN ST 91335

Application / Permit
21010-20000-00330
Plan Check / Job No.
B21VN00712
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 28'x 49'-1" ACCESSORY LIVING QUARTERS W/ ATT. 2-CAR GARAGE; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED; "COMPLY WITH DEPARTMENT ORDER effective date 02/17/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 SEAN SHAHMIRI
Corrections Issued 2/8/2021 SEAN SHAHMIRI
Quality Review Completed 2/10/2021 OMID HEDAYAT
Building Plans Picked Up 2/16/2021 APPLICANT
Applicant returned to address corrections 4/16/2021 SEAN SHAHMIRI
Applicant returned to address corrections 5/26/2021 SEAN SHAHMIRI
Applicant returned to address corrections 7/26/2021 SEAN SHAHMIRI
Applicant returned to address corrections 12/3/2021 SEAN SHAHMIRI
Plan Check Approved 12/15/2021 SEAN SHAHMIRI
Issued 2/4/2022 APPLICANT
CofO in Progress 10/3/2022 JEFFREY BULL
Permit Finaled 10/15/2022 MICHAEL SMITH
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 4/7/2021 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 8/3/2021 GABRIEL ROBLES
Sewer availability Cleared 8/3/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/7/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/13/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/14/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/9/2022 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/9/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/9/2022 Approved VINCENT HANLEY
PLUMBING-Rough 3/9/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/11/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/20/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval VINCENT HANLEY
Green Building Rough 4/20/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/18/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/6/2022 Corrections Issued VINCENT HANLEY
HVAC-Rough 6/6/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 6/6/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 6/17/2022 Partial Approval JEFFREY BULL
HVAC-Rough 6/17/2022 Partial Approval JEFFREY BULL
Interior/Exterior Lathing 6/17/2022 Partial Approval JEFFREY BULL
PLUMBING-Rough 6/17/2022 Partial Approval JEFFREY BULL
HVAC-Rough 7/25/2022 Partial Approval JEFFREY BULL
Insulation 7/29/2022 Approved JEFFREY BULL
Drywall Nailing 8/5/2022 Approved JEFFREY BULL
Green Building Rough 8/5/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 8/5/2022 Approved JEFFREY BULL
Sewer 8/13/2022 Off-Hour Fees Due
Underground Mechanical 8/15/2022 Approved JEFFREY BULL
Underground Mechanical 8/15/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 8/16/2022 Off-Hour Fees Due
Final 8/16/2022 Off-Hour Fees Due
Green Building Final 8/16/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 8/16/2022 Off-Hour Fees Due
Service/Power Release 8/16/2022 Off-Hour Fees Due
Smoke Detectors 8/16/2022 Off-Hour Fees Due
BUILDING-Rough-Frame 8/18/2022 Off-Hour Fees Due
Final 8/18/2022 Off-Hour Fees Due
Green Building Final 8/18/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 8/18/2022 Off-Hour Fees Due
Service/Power Release 8/18/2022 Off-Hour Fees Due
Smoke Detectors 8/18/2022 Off-Hour Fees Due
ELECTRICAL-Final 9/27/2022 Approved JEFFREY BULL
Final 9/27/2022 Corrections Issued JEFFREY BULL
Green Building Final 9/27/2022 Approved JEFFREY BULL
HVAC-Final 9/27/2022 Approved JEFFREY BULL
PLUMBING-Final 9/27/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Not Ready JEFFREY BULL
Service/Power Release 9/27/2022 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 9/27/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 9/27/2022 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 9/30/2022 Approved JEFFREY BULL
Final 9/30/2022 OK to Issue CofO JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved JEFFREY BULL
Service/Power Release 9/30/2022 Approved JEFFREY BULL