20211 W LIVERPOOL WAY 91326

Certificate Information: 20211 W LIVERPOOL WAY 91326

Application / Permit
21010-20000-00295
Plan Check / Job No.
B21VN00655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #652 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 9/21/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 NILOOFAR MEHRAIN
Corrections Issued 2/18/2021 NILOOFAR MEHRAIN
Quality Review Completed 2/18/2021 CHON CHIO KUO
Building Plans Picked Up 2/26/2021 APPLICANT
Plan Check Approved 9/16/2021 NILOOFAR MEHRAIN
Issued 9/21/2021 APPLICANT
CofO in Progress 10/5/2022 JEFFREY PARD
Permit Finaled 10/6/2022 MICHAEL SMITH
CofO Issued 10/6/2022 MICHAEL SMITH
Permit Finaled 10/6/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 9/1/2021 DANG NGUYEN
Address approval Cleared 9/1/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/1/2021 LEE GUILBEAUX
Miscellaneous Cleared 9/1/2021 DANG NGUYEN
Miscellaneous Cleared 9/1/2021 DANG NGUYEN
Miscellaneous Cleared 9/1/2021 DANG NGUYEN
Permit Cleared 9/1/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/1/2021 LEE GUILBEAUX
Sewer availability Cleared 9/1/2021 LEE GUILBEAUX
Specific Plan Cleared 9/1/2021 DANG NGUYEN
Tract Map conditions Cleared 9/1/2021 DANG NGUYEN
ZA Case Cleared 9/1/2021 DANG NGUYEN
ZA Case Cleared 9/1/2021 DANG NGUYEN
ZI Cleared 9/1/2021 DANG NGUYEN
Public Works-Highway Ded. Cleared 9/1/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/9/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 9/10/2021 ROBERT DUFF
GPI Written Notices Cleared 9/15/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 9/15/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/19/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 1/20/2022 Approved SEAN WIRCH
Deputy Reinf. Concrete 1/21/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Corrections Issued SEAN WIRCH
Sewer 4/14/2022 Approved SEAN WIRCH
Deputy Drilled-In Anchors 5/13/2022 Approved SEAN WIRCH
Deputy Wood Construction 5/23/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 6/10/2022 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Rough 6/10/2022 Approved SEAN WIRCH
Green Building Rough 6/10/2022 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 6/10/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 6/10/2022 Partial Approval SEAN WIRCH
PLUMBING-Rough 6/10/2022 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 6/10/2022 Approved SEAN WIRCH
PLUMBING-Rough 6/15/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 6/27/2022 Approved HENRY KIM
Drywall Nailing 6/27/2022 Approved HENRY KIM
Green Building Rough 6/27/2022 Approved HENRY KIM
Interior/Exterior Lathing 7/18/2022 Approved SEAN WIRCH
Gas Test 7/27/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved HENRY KIM
Service/Power Release 9/21/2022 Approved SEAN WIRCH
ELECTRICAL-Final 10/4/2022 Approved JEFFREY PARD
Final 10/4/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 10/4/2022 Approved JEFFREY PARD
HVAC-Final 10/4/2022 Approved JEFFREY PARD
PLUMBING-Final 10/4/2022 Approved JEFFREY PARD
Smoke Detectors 10/4/2022 Approved JEFFREY PARD