1650 S WELLESLEY AVE 90025
Certificate Information: 1650 S WELLESLEY AVE 90025
- Application / Permit
- 21010-20000-00291
- Plan Check / Job No.
- B21VN00651
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 29'-6" x 62'-9" TWO-STORY SINGLE FAMILY DWELLING W/ ROOF TOP AND ATT. 2-CAR GARAGE; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | SEAN SHAHMIRI |
| Corrections Issued | 2/17/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 2/26/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 12/20/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/20/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/7/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 3/22/2022 | SEAN SHAHMIRI |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | KIRK SANDERS |
| Permit Finaled | 6/25/2024 | DANIEL ORRANTE |
| CofO Issued | 6/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2021 | DINAH GARIN |
| Permit | Cleared | 5/18/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/26/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 6/22/2021 | KEVIN ARUCAN |
| Trees in Parkway | Cleared | 7/29/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/15/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/16/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | DINAH GARIN |
Contact Information
| Contractor | K Construction; Lic. No.: 566451-B | 4966 TOPANGA CANYON BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 11/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 11/17/2022 | Corrections Issued | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 11/21/2022 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/21/2022 | Partial Approval | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 11/29/2022 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Conditional Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/14/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 4/5/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| Gas Test | 4/5/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 4/5/2023 | Conditional Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/10/2023 | No Access for Inspection | JEREMY TODD |
| Green Building Rough | 4/10/2023 | No Access for Inspection | JEREMY TODD |
| HVAC-Rough | 4/10/2023 | No Access for Inspection | JEREMY TODD |
| Verify Sprinkler Sign Off | 4/10/2023 | No Access for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Approval | CLAYTON GRAHAM |
| PLUMBING-Rough | 4/18/2023 | Approved | CLAYTON GRAHAM |
| Wood Frame | 4/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 4/28/2023 | Corrections Issued | DANIEL ORRANTE |
| Green Building Rough | 4/28/2023 | Approved | DANIEL ORRANTE |
| HVAC-Rough | 4/28/2023 | Corrections Issued | DANIEL ORRANTE |
| Verify Sprinkler Sign Off | 4/28/2023 | Approved | DANIEL ORRANTE |
| Insulation | 5/9/2023 | No Access for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 5/9/2023 | Approved | DANIEL ORRANTE |
| Insulation | 5/15/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/1/2023 | Not Ready for Inspection | DANIEL ORRANTE |
| ELECTRICAL-Rough | 6/1/2023 | Not Ready for Inspection | DANIEL ORRANTE |
| HVAC-Rough | 6/1/2023 | Not Ready for Inspection | DANIEL ORRANTE |
| PLUMBING-Rough | 6/1/2023 | Not Ready for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 6/2/2023 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 6/2/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 6/2/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 6/6/2023 | No Access for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 6/6/2023 | No Access for Inspection | JESUS PINEDA |
| Wood Frame | 6/6/2023 | No Access for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Insulation | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/4/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/21/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 8/30/2023 | Partial Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/2/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 10/2/2023 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 10/2/2023 | Corrections Issued | MICHAEL PELHAM |
| Insulation | 10/2/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 10/2/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 10/2/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 10/11/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | MICHAEL PELHAM |
| Drywall Nailing | 10/17/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 11/6/2023 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 11/6/2023 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 3/28/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/28/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Special/Order Compliance | 3/28/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Final | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Required | ASHLEY THOMPSON |
| Service/Power Release | 4/5/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 4/5/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/15/2024 | Approved | ASHLEY THOMPSON |
| Final | 4/15/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 4/15/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 4/15/2024 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 4/15/2024 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 4/15/2024 | Approved | ASHLEY THOMPSON |
| Final | 5/14/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 5/14/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Final | 5/14/2024 | Corrections Issued | KIRK SANDERS |
| Final | 5/22/2024 | OK to Issue CofO | KIRK SANDERS |