4805 S FIGUEROA ST 90037

Certificate Information: 4805 S FIGUEROA ST 90037

Application / Permit
21010-20000-00285
Plan Check / Job No.
B21VN00640
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Car Wash
Work Description
(N) VACUUM CANOPY (24' X 16'-10") ACCESSORY TO (E) CAR RENTAL
Permit Issued
Issued on 9/24/2021
Issuing Office
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 2/22/2021 APPLICANT
Corrections Issued 2/23/2021 NILOOFAR MEHRAIN
Quality Review Completed 5/6/2021 CHON CHIO KUO
Plan Check Approved 7/6/2021 NILOOFAR MEHRAIN
Issued 9/24/2021 APPLICANT
TCO Issued (Expire Date: 05-01-2023) 11/2/2022 TED RIES
CofO in Progress 3/29/2023 ERNESTO CORRAL
CofO Issued 3/29/2023 ERNESTO CORRAL
Permit Finaled 3/29/2023 ERNESTO CORRAL

Permit Application Clearance Information

Automotive Use Cleared 4/8/2021 NOAH MCCOY
Automotive Use Cleared 4/8/2021 NOAH MCCOY
Comm Cor/Mini-Mall Cleared 4/8/2021 NOAH MCCOY
Comm Cor/Mini-Mall Cleared 4/8/2021 NOAH MCCOY
Miscellaneous Cleared 4/8/2021 NOAH MCCOY
Community Plan Implem. Overlay Cleared 5/20/2021 THOMAS LANG
DAS Clearance Cleared 5/20/2021 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 5/20/2021 THOMAS LANG
Sewer availability Cleared 5/20/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 5/24/2021 THOMAS LANG
Community Plan Implem. Overlay Cleared 6/8/2021 RAFAEL FONTES
Redevelopment Project Area Cleared 6/10/2021 DAVID URITA
ZI Cleared 6/10/2021 DAVID URITA
Automotive Use Cleared 6/23/2021 NOAH MCCOY

Contact Information

Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2022 Not Ready for Inspection TED RIES
Piling/Pier/Caisson 4/1/2022 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 4/8/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/14/2022 Partial Approval JAMES POWERS
Final 7/21/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/21/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Not Ready JAMES POWERS
Smoke Detectors 7/21/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/21/2022 Approved JAMES POWERS
Wood Frame 7/21/2022 Approved JAMES POWERS
Final 9/27/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV No Gas JAMES POWERS
Special/Order Compliance 9/27/2022 Approved JAMES POWERS
Final 3/29/2023 OK to Issue CofO ERNESTO CORRAL