17049 W LABRADOR ST 91325
Certificate Information: 17049 W LABRADOR ST 91325
- Application / Permit
- 21010-20000-00231
- Plan Check / Job No.
- B21VN00563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'0"X45'0" IRREGULAR SHAPED 1-STORY ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | MARVEL DELACRUZ |
| Corrections Issued | 2/17/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 2/19/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| Applicant returned to address corrections | 6/23/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 6/25/2021 | MARVEL DELACRUZ |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | JAVIER RAMOS JR |
| Permit Finaled | 7/23/2022 | MICHAEL SMITH |
| CofO Issued | 7/23/2022 | MICHAEL SMITH |
| Permit Finaled | 7/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/22/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 3/2/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/2/2021 | WALTER RAMIREZ |
| Miscellaneous | Cleared | 5/5/2021 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 5/13/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/14/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | ADRIAN CASTRO |
| Green Code | Cleared | 6/23/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nguyen,, Quynh Anh; Lic. No.: C58592 | 12000 MIRANDA ST VALLEY VILLAGE, CA 91607 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2021 | Partial Approval | MARK JOHNSON |
| Sewer | 8/31/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 8/31/2021 | Approved | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 9/7/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 9/21/2021 | Approved | MARK JOHNSON |
| Wood Frame | 9/21/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/28/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 9/28/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 9/28/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 9/28/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 10/6/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/6/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Wood Frame | 12/22/2021 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 12/29/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/29/2021 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/29/2021 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/4/2022 | Approved | MARK JOHNSON |
| Drywall Nailing | 1/10/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/10/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/12/2022 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 3/30/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/30/2022 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/30/2022 | Approved | MICHAEL TEMPLE |
| Green Building Final | 3/30/2022 | Approved | MICHAEL TEMPLE |
| HVAC-Final | 3/30/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 3/30/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 3/30/2022 | Not Required | MICHAEL TEMPLE |
| Smoke Detectors | 3/30/2022 | Approved | MICHAEL TEMPLE |
| Final | 4/27/2022 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 4/27/2022 | Not Required | RAUL OLAGI |
| ELECTRICAL-Final | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Final | 6/6/2022 | Conditional Approval | JAVIER RAMOS JR |
| HVAC-Final | 6/6/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/6/2022 | Approved | JAVIER RAMOS JR |