17049 W LABRADOR ST 91325

Certificate Information: 17049 W LABRADOR ST 91325

Application / Permit
21010-20000-00231
Plan Check / Job No.
B21VN00563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'0"X45'0" IRREGULAR SHAPED 1-STORY ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 MARVEL DELACRUZ
Corrections Issued 2/17/2021 MARVEL DELACRUZ
Quality Review Completed 2/19/2021 STEVEN KIM
Building Plans Picked Up 2/19/2021 APPLICANT
Applicant returned to address corrections 6/23/2021 MARVEL DELACRUZ
Plan Check Approved 6/25/2021 MARVEL DELACRUZ
Issued 6/25/2021 APPLICANT
CofO in Progress 7/21/2022 JAVIER RAMOS JR
Permit Finaled 7/23/2022 MICHAEL SMITH
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/22/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/22/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/22/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/2/2021 WALTER RAMIREZ
Construction within easement Cleared 3/2/2021 WALTER RAMIREZ
Miscellaneous Cleared 5/5/2021 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 5/13/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/14/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/14/2021 ADRIAN CASTRO
Green Code Cleared 6/23/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2021 Partial Approval MARK JOHNSON
Sewer 8/31/2021 Approved MARK JOHNSON
Underground Mechanical 8/31/2021 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 9/7/2021 Approved MARK JOHNSON
PLUMBING-Rough 9/21/2021 Approved MARK JOHNSON
Wood Frame 9/21/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/28/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 9/28/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 9/28/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 9/28/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 9/28/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/6/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/6/2021 Approved MICHEL ABAJAN
Green Building Rough 10/6/2021 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 12/22/2021 Approved MICHAEL TEMPLE
Green Building Rough 12/22/2021 Not Ready for Inspection MICHAEL TEMPLE
Wood Frame 12/22/2021 Approved MICHAEL TEMPLE
Green Building Rough 12/29/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/29/2021 Approved JESUS RODRIGUEZ
PLUMBING-Rough 12/29/2021 Approved JESUS RODRIGUEZ
Insulation 1/4/2022 Approved MARK JOHNSON
Drywall Nailing 1/10/2022 Approved JESUS RODRIGUEZ
Shower Pan 1/10/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/12/2022 Approved MARK JOHNSON
ELECTRICAL-Final 3/30/2022 Approved MICHAEL TEMPLE
Final 3/30/2022 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 3/30/2022 Approved MICHAEL TEMPLE
Green Building Final 3/30/2022 Approved MICHAEL TEMPLE
HVAC-Final 3/30/2022 Approved MICHAEL TEMPLE
PLUMBING-Final 3/30/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved MICHAEL TEMPLE
Service/Power Release 3/30/2022 Not Required MICHAEL TEMPLE
Smoke Detectors 3/30/2022 Approved MICHAEL TEMPLE
Final 4/27/2022 Corrections Issued RAUL OLAGI
Service/Power Release 4/27/2022 Not Required RAUL OLAGI
ELECTRICAL-Final 6/6/2022 Approved JAVIER RAMOS JR
Final 6/6/2022 Conditional Approval JAVIER RAMOS JR
HVAC-Final 6/6/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 6/6/2022 Approved JAVIER RAMOS JR