14699 W CHATSWORTH DR 91345
Certificate Information: 14699 W CHATSWORTH DR 91345
- Application / Permit
- 21010-20000-00211
- Plan Check / Job No.
- B21VN00512
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 36'-4" X 22'-5" DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED ONE-CAR GARAGE PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2021 | ROSENDO MEDINA |
| Corrections Issued | 2/7/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 9/21/2021 | ROSENDO MEDINA |
| Plan Check Approved | 10/18/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 10/18/2021 | APPLICANT |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 3/3/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/22/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 8/9/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/12/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/13/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD SUITE 227 ENCINO, CA 91436 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/29/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/7/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 9/7/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 9/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 9/13/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 9/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 9/20/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 9/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/30/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/4/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/7/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/23/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 11/23/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 11/23/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/9/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/9/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/31/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/31/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 10/31/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 2/11/2025 | Partial Approval | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | ROBERT GOLD |
| Final | 3/3/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 3/3/2025 | Approved | JENNIFER RABUCHIN |