9529 N COLUMBUS AVE 91343

Certificate Information: 9529 N COLUMBUS AVE 91343

Application / Permit
21010-20000-00208
Plan Check / Job No.
B21VN00507
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-0" X 44'-11" 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/10/2023
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 ARTIN ZARUKIAN
Corrections Issued 1/30/2021 ARTIN ZARUKIAN
Plan Check Approved 2/10/2023 HAYATO TSUCHIYA
Issued 2/10/2023 APPLICANT
CofO in Progress 1/31/2024 JENNIFER RABUCHIN
Permit Finaled 3/18/2024 RUBEN SALAS
CofO Issued 3/18/2024 RUBEN SALAS
Permit Finaled 3/18/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 10/19/2021 SARAH YOUSSEF
Address approval Cleared 1/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/14/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/14/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 3/8/2022 LARRY REDDEN
Roof/Waste drainage to street Cleared 2/10/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2023 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/24/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/24/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/3/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/3/2023 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 4/7/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/7/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/21/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/4/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 5/4/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/4/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/9/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/9/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/9/2023 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/9/2023 Approved JENNIFER RABUCHIN
Insulation 5/11/2023 Approved JENNIFER RABUCHIN
Sewer 5/11/2023 Partial Approval JENNIFER RABUCHIN
Shower Pan 5/12/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 5/18/2023 Approved JENNIFER RABUCHIN
Gas Test 5/22/2023 Partial Approval JENNIFER RABUCHIN
Sewer 5/22/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 5/22/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/5/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/16/2024 Approved JENNIFER RABUCHIN
Final 1/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/16/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 1/16/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/30/2024 Approved JENNIFER RABUCHIN
Final 1/30/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/30/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/30/2024 Approved JENNIFER RABUCHIN
Service/Power Release 1/30/2024 Approved JENNIFER RABUCHIN