11148 N MONTGOMERY AVE 91344

Certificate Information: 11148 N MONTGOMERY AVE 91344

Application / Permit
21010-20000-00200
Plan Check / Job No.
B21VN00472
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 14'4" X 52' DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E), ALL WORK PER WFPP
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 5/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 RARES BODEA
Corrections Issued 1/28/2021 RARES BODEA
Building Plans Picked Up 2/8/2021 APPLICANT
Applicant returned to address corrections 7/19/2021 RARES BODEA
Plan Check Approved 7/21/2021 RARES BODEA
Issued 7/21/2021 APPLICANT
CofO in Progress 4/28/2022 RAUL OLAGI
Permit Finaled 5/2/2022 RONALD MYRICK
CofO Issued 5/2/2022 RONALD MYRICK
Permit Finaled 5/2/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/8/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/8/2021 ADRIAN CASTRO
Sewer availability Cleared 2/8/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/19/2021 KURT CORRAL
Construction near power lines Cleared 5/7/2021 RIDWAN HARDY
Construction within easement Cleared 5/7/2021 RIDWAN HARDY
Low Impact Development Cleared 7/4/2021 MARTIN FRAGOSO
GPI Written Notices Cleared 7/19/2021 RARES BODEA
Grading Pre-Inspection Cleared 7/19/2021 RARES BODEA
Roof/Waste drainage to street Cleared 7/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/16/2021 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 9/9/2021 Approved MARK JOHNSON
PLUMBING-Rough 9/9/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval MARK JOHNSON
Sewer 10/21/2021 Approved MARK JOHNSON
Underground Mechanical 10/21/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 10/21/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 10/27/2021 Approved MARK JOHNSON
HVAC-Rough 10/27/2021 Approved MARK JOHNSON
PLUMBING-Rough 10/27/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/1/2021 Approved MARK JOHNSON
Green Building Rough 11/1/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 11/1/2021 Approved MARK JOHNSON
Insulation 11/4/2021 Approved MARK JOHNSON
Drywall Nailing 11/12/2021 Approved MARK JOHNSON
ELECTRICAL-Final 2/18/2022 Corrections Issued RAUL OLAGI
Final 2/18/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/18/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 2/18/2022 Corrections Issued RAUL OLAGI
Final 3/8/2022 Corrections Issued MICHAEL TEMPLE
Green Building Final 3/8/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved MICHAEL TEMPLE
Service/Power Release 3/8/2022 Not Ready for Inspection MICHAEL TEMPLE
Smoke Detectors 3/8/2022 Approved MICHAEL TEMPLE
Final 3/16/2022 Corrections Issued RAUL OLAGI
Service/Power Release 3/16/2022 Not Ready for Inspection RAUL OLAGI
Final 4/20/2022 Corrections Issued RAUL OLAGI
Service/Power Release 4/20/2022 Not Ready for Inspection RAUL OLAGI
Final 4/27/2022 OK to Issue CofO RAUL OLAGI
Service/Power Release 4/27/2022 Approved RAUL OLAGI