11148 N MONTGOMERY AVE 91344
Certificate Information: 11148 N MONTGOMERY AVE 91344
- Application / Permit
- 21010-20000-00200
- Plan Check / Job No.
- B21VN00472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 14'4" X 52' DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E), ALL WORK PER WFPP
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- Current Status
- CofO Issued on 5/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | RARES BODEA |
| Corrections Issued | 1/28/2021 | RARES BODEA |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| Applicant returned to address corrections | 7/19/2021 | RARES BODEA |
| Plan Check Approved | 7/21/2021 | RARES BODEA |
| Issued | 7/21/2021 | APPLICANT |
| CofO in Progress | 4/28/2022 | RAUL OLAGI |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
| CofO Issued | 5/2/2022 | RONALD MYRICK |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/8/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 3/19/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 5/7/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/4/2021 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 7/19/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 7/19/2021 | RARES BODEA |
| Roof/Waste drainage to street | Cleared | 7/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/11/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 9/9/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 9/9/2021 | Partial Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Partial Approval | MARK JOHNSON |
| Sewer | 10/21/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 10/21/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 10/21/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 10/27/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 10/27/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 10/27/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 11/1/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 11/1/2021 | Approved | MARK JOHNSON |
| Insulation | 11/4/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 11/12/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 2/18/2022 | Corrections Issued | RAUL OLAGI |
| Final | 2/18/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 2/18/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 2/18/2022 | Corrections Issued | RAUL OLAGI |
| Final | 3/8/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 3/8/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 3/8/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Smoke Detectors | 3/8/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/16/2022 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 3/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| Final | 4/20/2022 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 4/20/2022 | Not Ready for Inspection | RAUL OLAGI |
| Final | 4/27/2022 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 4/27/2022 | Approved | RAUL OLAGI |