3610 N WRIGHTWOOD DR 91604

Certificate Information: 3610 N WRIGHTWOOD DR 91604

Application / Permit
21010-20000-00161
Plan Check / Job No.
B21VN00335
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 675 SQ. FT. RECREATION ROOM WITH TRELLIS PORCH & STORAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
Issued on 10/7/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 COLIN LOREDO
Corrections Issued 2/9/2021 COLIN LOREDO
Quality Review Completed 2/18/2021 OMID HEDAYAT
Building Plans Picked Up 2/22/2021 APPLICANT
Applicant returned to address corrections 7/15/2021 COLIN LOREDO
Applicant returned to address corrections 9/16/2021 COLIN LOREDO
Applicant returned to address corrections 9/30/2021 COLIN LOREDO
Plan Check Approved 10/5/2021 COLIN LOREDO
Issued 10/7/2021 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 2/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 2/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 2/23/2021 JOHN TRIANTAFYLLOS
BHO/Hillside ordinance Cleared 2/23/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/23/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/23/2021 JOHN TRIANTAFYLLOS
ZA Case Cleared 2/24/2021 LAUREN PADICK
Hydrant and Access approval Cleared 4/15/2021 KURT CORRAL
Specific Plan Cleared 7/13/2021 OLGA AYALA
Low Impact Development Cleared 8/27/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/7/2021 GABRIEL ROBLES

Contact Information

Contractor Kcc Design Build, Inc; Lic. No.: 932319-B 333 N CURSON AVENUE      LOS ANGELES, CA 90036
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/13/2021 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/26/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/28/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/7/2022 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 2/7/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 2/9/2022 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/11/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 2/11/2022 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 2/11/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/14/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/4/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 5/4/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 5/4/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/20/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 5/20/2022 Approved BRIAN SULLIVAN
Insulation 5/20/2022 Approved BRIAN SULLIVAN
Drywall Nailing 5/27/2022 Approved RAUL BARAJAS
Green Building Rough 5/27/2022 Approved RAUL BARAJAS
Shower Pan 7/21/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 9/23/2022 Not Ready for Inspection BRIAN SULLIVAN