13615 N BORDEN AVE 91342

Certificate Information: 13615 N BORDEN AVE 91342

Application / Permit
21010-20000-00149
Plan Check / Job No.
B21VN00308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-6" X 55'-6" IRREGULAR SHAPE 2-STORY AACCESSORY DWELLING UNIT W/ATT 2-CAR GARAGE PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 7/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 PARISA ZAHABI
Corrections Issued 2/20/2021 PARISA ZAHABI
Quality Review Completed 2/24/2021 OMID HEDAYAT
Applicant returned to address corrections 8/26/2021 PARISA ZAHABI
Plan Check Approved 10/21/2021 PARISA ZAHABI
Issued 10/27/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 6/25/2024 KEVIN BERBERYAN
No Progress 7/5/2024 ROBERT GOLD
CofO in Progress 7/5/2024 ROBERT GOLD
CofO in Progress 7/16/2024 ROBERT GOLD
CofO in Progress 7/17/2024 ROBERT GOLD
No Progress 7/17/2024 ROBERT GOLD
CofO in Progress 7/17/2024 ROBERT GOLD
Permit Finaled 7/19/2024 RUBEN SALAS
CofO Issued 7/19/2024 RUBEN SALAS
Permit Finaled 7/19/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/29/2021 JOHN CONNEALLY
Address approval Cleared 7/30/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/16/2021 GABRIEL ROBLES
Sewer availability Cleared 8/16/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/14/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/18/2021 GABRIEL ROBLES

Contact Information

Contractor Aligned Construction Company Inc; Lic. No.: 894983-B 8905 GLENOAKS BLVD UNIT L      SUN VALLEY, CA 91352
Engineer Van, Valkenburg, John Marshall; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 11/30/2021 Partial Approval JOHN HAYES
Underground Mechanical 11/30/2021 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 12/8/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 4/5/2022 Partial Approval JOHN HAYES
ELECTRICAL-Rough 4/5/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/5/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/5/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 4/5/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/19/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/19/2022 Approved JOHN HAYES
Interior/Exterior Lathing 4/19/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 4/19/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 4/19/2022 Approved JOHN HAYES
Insulation 4/25/2022 Approved JOHN HAYES
Interior/Exterior Lathing 5/11/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 5/3/2024 Approved KEVIN BERBERYAN
Drywall Nailing 5/3/2024 Approved KEVIN BERBERYAN
Final 5/3/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 5/3/2024 Approved KEVIN BERBERYAN
Green Building Final 5/3/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 5/3/2024 Not Required KEVIN BERBERYAN
Smoke Detectors 5/3/2024 Approved KEVIN BERBERYAN
Final 6/11/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 6/11/2024 Approved KEVIN BERBERYAN
Service/Power Release 6/11/2024 Approved KEVIN BERBERYAN
Final 7/16/2024 Corrections Issued ROBERT GOLD