20378 W MARLOW LANE 91326

Certificate Information: 20378 W MARLOW LANE 91326

Application / Permit
21010-20000-00148
Plan Check / Job No.
B21VN00304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
SUPPLEMENTAL TO 20010-20000-02508: TO ADD 17'X13'-5" TRELLIS TO THE REAR OF SFD
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
Issued on 5/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 DAWN MC NULTY
Corrections Issued 2/24/2021 DAWN MC NULTY
Quality Review Completed 2/24/2021 CHON CHIO KUO
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 4/21/2021 DAWN MC NULTY
Plan Check Approved 5/3/2021 DAWN MC NULTY
Issued 5/3/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/22/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/22/2021 LEE GUILBEAUX
"T" removal Cleared 4/29/2021 DANG NGUYEN
CPC Cleared 4/29/2021 DANG NGUYEN
Miscellaneous Cleared 4/29/2021 DANG NGUYEN
Miscellaneous Cleared 4/29/2021 DANG NGUYEN
Miscellaneous Cleared 4/29/2021 DANG NGUYEN
Specific Plan Cleared 4/29/2021 DANG NGUYEN
Tract Map conditions Cleared 4/29/2021 DANG NGUYEN
ZA Case Cleared 4/29/2021 DANG NGUYEN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2021 Approved SEAN WIRCH
BUILDING-Rough-Frame 9/19/2022 Approved JEFFREY PARD
Drywall Nailing 9/19/2022 Approved JEFFREY PARD
Final 9/19/2022 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 9/19/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 9/19/2022 Approved JEFFREY PARD
Final 10/5/2022 Not Ready for Inspection JEFFREY PARD
Final 3/23/2023 Partial Approval JEFFREY PARD