7331 N BAIRD AVE 91335
Certificate Information: 7331 N BAIRD AVE 91335
- Application / Permit
- 21010-20000-00145
- Plan Check / Job No.
- B21VN00297
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 33'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | PARISA ZAHABI |
| Corrections Issued | 2/17/2021 | PARISA ZAHABI |
| Quality Review Completed | 2/24/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/22/2021 | PARISA ZAHABI |
| Plan Check Approved | 6/21/2021 | PARISA ZAHABI |
| Issued | 6/21/2021 | APPLICANT |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | VINCENT HANLEY |
| Permit Finaled | 4/27/2022 | MICHAEL SMITH |
| CofO Issued | 4/27/2022 | MICHAEL SMITH |
| Permit Finaled | 4/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/6/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 5/14/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 8/4/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Underground Mechanical | 11/22/2021 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Wood Construction | 11/23/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/2/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/2/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 12/2/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/2/2021 | Approved | VINCENT HANLEY |
| Insulation | 12/9/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/9/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 12/17/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/17/2021 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/6/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 1/6/2022 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 1/13/2022 | Approved | JUSTIN HAWLEY |
| Final | 2/16/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/16/2022 | Not Ready for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 2/16/2022 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 2/16/2022 | Approved | VINCENT HANLEY |
| Final | 3/21/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 3/21/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/21/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 3/30/2022 | Approved | VINCENT HANLEY |
| Final | 3/30/2022 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/30/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/30/2022 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/30/2022 | Approved | VINCENT HANLEY |