7005 N ETHEL AVE 91605
Certificate Information: 7005 N ETHEL AVE 91605
- Application / Permit
- 21010-20000-00136
- Plan Check / Job No.
- B21VN00286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19'-6" x 25'-11" DET. TWO-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/21/2022
- Issuing Office
- Current Status
- Issued on 2/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SEAN SHAHMIRI |
| Corrections Issued | 1/30/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 2/9/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 2/10/2021 | APPLICANT |
| Applicant returned to address corrections | 9/29/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 12/16/2021 | SEAN SHAHMIRI |
| Issued | 2/21/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/10/2021 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 6/22/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 6/22/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 9/9/2021 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 9/12/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 9/13/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
| Engineer | Hsiao,, Stephanie; Lic. No.: C75937 | 255 N MICHIGAN AVE #5 PASADENA, CA 91106 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 5/12/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/31/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 9/7/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Rough | 9/7/2022 | Not Ready for Inspection | RAFAEL CORTES |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | RAFAEL CORTES |
| ELECTRICAL-Rough | 9/13/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 9/13/2022 | Corrections Issued | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 9/16/2022 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 9/16/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 10/12/2022 | Corrections Issued | RAFAEL CORTES |
| Insulation | 10/14/2022 | Conditional Approval | ROBERT GOLD |
| Drywall Nailing | 10/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 10/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/7/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 8/16/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 12/21/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 12/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 1/17/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/27/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 3/1/2024 | Approved | JOSE AVILA |
| Service/Power Release | 3/1/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/14/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/14/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/14/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 8/14/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/14/2024 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/14/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | GAREN HAYRAPETYAN |
| Final | 12/4/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 5/7/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 5/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |