20402 W WILLOUGHBY LANE 91326

Certificate Information: 20402 W WILLOUGHBY LANE 91326

Application / Permit
21010-20000-00118
Plan Check / Job No.
B21VN00258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #653 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 9/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 NILOOFAR MEHRAIN
Corrections Issued 2/4/2021 NILOOFAR MEHRAIN
Quality Review Completed 2/4/2021 CHON CHIO KUO
Building Plans Picked Up 2/11/2021 APPLICANT
Plan Check Approved 9/14/2021 NILOOFAR MEHRAIN
Issued 9/20/2021 APPLICANT
CofO in Progress 9/16/2022 HENRY KIM
CofO Issued 9/21/2022 MICHAEL SMITH
Permit Finaled 9/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/2/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/2/2021 LEE GUILBEAUX
Permit Cleared 8/2/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/2/2021 LEE GUILBEAUX
Sewer availability Cleared 8/2/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/2/2021 LEE GUILBEAUX
"T" removal Cleared 8/4/2021 DANG NGUYEN
Miscellaneous Cleared 8/4/2021 DANG NGUYEN
Miscellaneous Cleared 8/4/2021 DANG NGUYEN
Miscellaneous Cleared 8/4/2021 DANG NGUYEN
Miscellaneous Cleared 8/4/2021 DANG NGUYEN
Specific Plan Cleared 8/4/2021 DANG NGUYEN
Tract Map conditions Cleared 8/4/2021 DANG NGUYEN
ZA Case Cleared 8/4/2021 DANG NGUYEN
ZA Case Cleared 8/4/2021 DANG NGUYEN
ZI Cleared 8/4/2021 DANG NGUYEN
Low Impact Development Cleared 8/12/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 9/6/2021 ROBERT DUFF
GPI Written Notices Cleared 9/14/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 9/14/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/23/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 2/2/2022 Approved SEAN WIRCH
Deputy Reinf. Concrete 2/4/2022 Approved SEAN WIRCH
Sewer 2/11/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Not Ready for Inspection HENRY KIM
Underground Mechanical 3/16/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval SEAN WIRCH
Pre-Inspection 3/21/2022 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval SEAN WIRCH
Pre-Inspection 3/22/2022 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 5/10/2022 Approved SEAN WIRCH
HVAC-Rough 5/10/2022 Approved SEAN WIRCH
PLUMBING-Rough 5/10/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 5/11/2022 Approved SEAN WIRCH
Green Building Rough 5/11/2022 Approved SEAN WIRCH
Verify Sprinkler Sign Off 5/11/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 5/19/2022 Partial Approval SEAN WIRCH
Drywall Nailing 5/20/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 6/2/2022 Approved SEAN WIRCH
Gas Test 6/10/2022 Approved SEAN WIRCH
Service/Power Release 7/8/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved SEAN WIRCH
ELECTRICAL-Final 8/4/2022 Corrections Issued HENRY KIM
PLUMBING-Final 9/1/2022 Approved HENRY KIM
ELECTRICAL-Final 9/9/2022 Approved HENRY KIM
HVAC-Final 9/9/2022 Approved HENRY KIM
ELECTRICAL-Final 9/15/2022 Approved HENRY KIM
Final 9/15/2022 OK to Issue CofO HENRY KIM
Green Building Final 9/15/2022 Approved HENRY KIM
Smoke Detectors 9/15/2022 Approved HENRY KIM