8603 N COLLETT AVE 91343
Certificate Information: 8603 N COLLETT AVE 91343
- Application / Permit
- 21010-20000-00081
- Plan Check / Job No.
- B21VN00193
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT ( 22'-8"X33'-0") PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/18/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 1/20/2021 | APPLICANT |
| Plan Check Approved | 8/26/2021 | MOHAMMAD ESMAILI |
| Issued | 9/17/2021 | APPLICANT |
| CofO in Progress | 3/24/2022 | RAUL OLAGI |
| CofO Issued | 3/24/2022 | RONALD MYRICK |
| Permit Finaled | 3/24/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/25/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 4/15/2021 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 5/24/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 5/27/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Pavlovich Construction Co; Lic. No.: 388868-B | 22817 VENTURA BLVD #1001 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 10/5/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 10/27/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 10/27/2021 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/1/2021 | Corrections Issued | RAUL OLAGI |
| Sewer | 11/1/2021 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 11/5/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 11/5/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/5/2021 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 11/5/2021 | Partial Approval | RAUL OLAGI |
| Sewer | 11/5/2021 | Approved | RAUL OLAGI |
| Insulation | 11/9/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/16/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/16/2021 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 11/16/2021 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/25/2022 | Corrections Issued | RAUL OLAGI |
| Final | 1/25/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/25/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 1/25/2022 | Corrections Issued | RAUL OLAGI |
| Final | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/4/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 2/4/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/16/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 2/23/2022 | Approved | RAUL OLAGI |
| Final | 2/23/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 2/23/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/23/2022 | Approved | RAUL OLAGI |
| Final | 3/23/2022 | OK to Issue CofO | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 3/23/2022 | Approved | RAUL OLAGI |