8603 N COLLETT AVE 91343

Certificate Information: 8603 N COLLETT AVE 91343

Application / Permit
21010-20000-00081
Plan Check / Job No.
B21VN00193
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT ( 22'-8"X33'-0") PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
Permit Issued
Issued on 9/17/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 MOHAMMAD ESMAILI
Corrections Issued 1/18/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 1/20/2021 APPLICANT
Plan Check Approved 8/26/2021 MOHAMMAD ESMAILI
Issued 9/17/2021 APPLICANT
CofO in Progress 3/24/2022 RAUL OLAGI
CofO Issued 3/24/2022 RONALD MYRICK
Permit Finaled 3/24/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 1/21/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/25/2021 ADRIAN CASTRO
Sewer availability Cleared 1/25/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/15/2021 MARTIN FRAGOSO
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 5/27/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Pavlovich Construction Co; Lic. No.: 388868-B 22817 VENTURA BLVD #1001      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2021 Approved JACK KARGODORIAN
Underground Mechanical 10/5/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval RAUL OLAGI
PLUMBING-Rough 10/27/2021 Approved RAUL OLAGI
Underground Mechanical 10/27/2021 Approved RAUL OLAGI
ELECTRICAL-Rough 11/1/2021 Corrections Issued RAUL OLAGI
HVAC-Rough 11/1/2021 Corrections Issued RAUL OLAGI
Sewer 11/1/2021 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 11/5/2021 Approved RAUL OLAGI
Green Building Rough 11/5/2021 Approved RAUL OLAGI
HVAC-Rough 11/5/2021 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 11/5/2021 Partial Approval RAUL OLAGI
Sewer 11/5/2021 Approved RAUL OLAGI
Insulation 11/9/2021 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/16/2021 Approved RAUL OLAGI
Drywall Nailing 11/16/2021 Approved RAUL OLAGI
HVAC-Rough 11/16/2021 Approved RAUL OLAGI
Verify Sprinkler Sign Off 11/16/2021 Approved RAUL OLAGI
ELECTRICAL-Final 1/25/2022 Corrections Issued RAUL OLAGI
Final 1/25/2022 Corrections Issued RAUL OLAGI
Green Building Final 1/25/2022 Corrections Issued RAUL OLAGI
HVAC-Final 1/25/2022 Corrections Issued RAUL OLAGI
Final 2/4/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/4/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 2/4/2022 Approved RAUL OLAGI
ELECTRICAL-Final 2/16/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Final 2/23/2022 Approved RAUL OLAGI
Final 2/23/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/23/2022 Approved RAUL OLAGI
PLUMBING-Final 2/23/2022 Approved RAUL OLAGI
Final 3/23/2022 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 3/23/2022 Approved RAUL OLAGI