18236 W ARMINTA ST 91335

Certificate Information: 18236 W ARMINTA ST 91335

Application / Permit
21010-20000-00043
Plan Check / Job No.
B21VN00070
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-0" X 27'-9" DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 6/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 JEROME MAGAT PALMA
Corrections Issued 1/26/2021 JEROME MAGAT PALMA
Quality Review Completed 2/16/2021 OMID HEDAYAT
Plan Check Approved 3/3/2022 JEROME MAGAT PALMA
Building Plans Picked Up 3/15/2022 APPLICANT
Issued 4/7/2022 APPLICANT
CofO in Progress 5/7/2024 JEFFREY BULL
Permit Finaled 6/5/2024 JOHN JANSON
CofO Issued 6/5/2024 JOHN JANSON
Permit Finaled 6/5/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/1/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/9/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/9/2021 DAGOVERTO GUERRERO
Miscellaneous Cleared 6/29/2021 STEVEN WECHSLER
ZA Case Cleared 6/29/2021 STEVEN WECHSLER
ZI Cleared 6/29/2021 STEVEN WECHSLER
Hydrant and Access approval Cleared 9/9/2021 JOHN CONNEALLY
Low Impact Development Cleared 1/10/2022 TA ANH
Roof/Waste drainage to street Cleared 1/11/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD STE 317      ENCINO, CA 91436

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/10/2022 Partial Approval VINCENT HANLEY
Underground Mechanical 5/10/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 5/16/2022 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/19/2022 Approved VINCENT HANLEY
Wood Frame 6/15/2022 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 7/7/2022 Partial Approval JEFFREY BULL
Green Building Rough 7/7/2022 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 7/7/2022 Not Ready for Inspection JEFFREY BULL
Wood Frame 7/7/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 8/30/2022 Approved JEFFREY BULL
HVAC-Rough 8/30/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 8/30/2022 Approved JEFFREY BULL
PLUMBING-Rough 8/30/2022 Approved JEFFREY BULL
Insulation 9/12/2022 Approved JEFFREY BULL
Drywall Nailing 9/16/2022 Approved KRISTEN CAUSEY
Shower Pan 10/12/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/24/2022 Approved JEFFREY BULL
Smoke Detectors 11/17/2022 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 12/20/2022 Approved JEFFREY BULL
Final 12/20/2022 Not Ready for Inspection JEFFREY BULL
Footing/Foundation/Slab 12/20/2022 Approved JEFFREY BULL
Green Building Final 12/20/2022 Approved JEFFREY BULL
Green Building Rough 12/20/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready JEFFREY BULL
Service/Power Release 12/20/2022 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 12/20/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 12/20/2022 Approved JEFFREY BULL
Final 4/11/2024 OK to Issue CofO JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 4/11/2024 Approved JEFFREY BULL
Special/Order Compliance 5/15/2024 Approved JEFFREY BULL