15712 W LUDLOW ST 91344

Certificate Information: 15712 W LUDLOW ST 91344

Application / Permit
21010-20000-00041
Plan Check / Job No.
B21VN00063
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU (49'-6" x 31'-0"),1190 SQFT per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 8/6/2024
Issuing Office
Valley
Current Status
CofO in Progress on 6/1/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/19/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 PETER MOSESIAN
Corrections Issued 2/11/2021 PETER MOSESIAN
Quality Review Completed 2/25/2021 OMID HEDAYAT
Building Plans Picked Up 3/12/2021 APPLICANT
Plan Check Approved 2/15/2024 PETER MOSESIAN
Issued 8/6/2024 APPLICANT
CofO in Progress 6/1/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Address approval Cleared 6/9/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/14/2022 CARLOS AGUILERA
Sewer availability Cleared 6/14/2022 CARLOS AGUILERA
Construction near power lines Cleared 10/19/2022 WALTER RAMIREZ
Low Impact Development Cleared 1/12/2024 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 1/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/13/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 4/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/23/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 4/25/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/29/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/2/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/8/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/11/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 6/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 6/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 6/11/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 6/16/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 6/17/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 6/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/15/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/18/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 7/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/30/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 7/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/12/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 8/12/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/12/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/19/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/19/2025 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 8/19/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/20/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/21/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 8/21/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/22/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/22/2025 Approved CHRISTOPHER ROJAS
Shower Pan 8/28/2025 Approved MICHAEL CORTEZ
Drywall Nailing 8/29/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/8/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/10/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/12/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/15/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 10/16/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 10/16/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Rec and Parks Fee Memo 10/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 11/17/2025 No Access for Inspection CHRISTOPHER ROJAS
HVAC-Final 11/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 11/17/2025 No Access for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 11/25/2025 Corrections Issued CHRISTOPHER ROJAS
Final 11/25/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 11/25/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 11/25/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Not Ready CHRISTOPHER ROJAS
ELECTRICAL-Final 12/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 12/1/2025 OK to Expire Permit CHRISTOPHER ROJAS
PLUMBING-Final 12/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 12/1/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 12/3/2025 Approved CHRISTOPHER ROJAS
Final 12/3/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 12/3/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 12/3/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 12/4/2025 No Access for Inspection MICHEL ABAJAN
Final 5/29/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 5/29/2026 Approved CHRISTOPHER ROJAS
MERV13>=Final 5/29/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 5/29/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 5/29/2026 Approved CHRISTOPHER ROJAS