15712 W LUDLOW ST 91344
Certificate Information: 15712 W LUDLOW ST 91344
- Application / Permit
- 21010-20000-00041
- Plan Check / Job No.
- B21VN00063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU (49'-6" x 31'-0"),1190 SQFT per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | PETER MOSESIAN |
| Corrections Issued | 2/11/2021 | PETER MOSESIAN |
| Quality Review Completed | 2/25/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| Plan Check Approved | 2/15/2024 | PETER MOSESIAN |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 6/1/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/14/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/19/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 1/12/2024 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/13/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/20/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/17/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 4/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/23/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/25/2025 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/2/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/8/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 6/11/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/11/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 6/16/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 6/17/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/27/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/15/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/18/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 7/18/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/18/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/18/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/21/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 7/30/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/30/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Insulation | 8/12/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 8/12/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 8/19/2025 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 8/19/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/20/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 8/21/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/21/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/22/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 8/22/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 8/28/2025 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 8/29/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/8/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/10/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/12/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Rec and Parks Fee Memo | 10/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/17/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 11/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/17/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 11/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 11/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 11/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 12/1/2025 | OK to Expire Permit | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 12/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/3/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 12/3/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 12/3/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/3/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 12/4/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 5/29/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 5/29/2026 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/29/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/29/2026 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/29/2026 | Approved | CHRISTOPHER ROJAS |