5530 N DONNA AVE 91356

Certificate Information: 5530 N DONNA AVE 91356

Application / Permit
21010-20000-00040
Plan Check / Job No.
B21VN00060
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(6) House of Worship
Work Description
NEW 75'8 1/4" X 110'11-1/2" TWO STORY HOUSE OF WORSHIP WITH ADMINISTRATIVE OFFICES AND ON-SITE LIVING QUARTERS FOR CLERGY, CARETAKERS AND GUESTS AND BASEMENT, ALL WORK PER ZA-2004-5664-CU, NFPA-13 FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/5/2023
Issuing Office
Current Status
Issued on 4/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 RARES BODEA
Corrections Issued 1/29/2021 RARES BODEA
Disabled Access Plans Picked Up 2/4/2021 APPLICANT
Green Plans Picked Up 2/4/2021 APPLICANT
Quality Review Completed 2/8/2021 STEVEN KIM
Building Plans Picked Up 2/9/2021 APPLICANT
Applicant returned to address corrections 11/22/2021 RARES BODEA
Applicant returned to address corrections 6/6/2022 RARES BODEA
Applicant returned to address corrections 7/21/2022 RARES BODEA
Applicant returned to address corrections 8/8/2022 RARES BODEA
Plan Check Approved 9/28/2022 RARES BODEA
Issued 4/5/2023 APPLICANT
TCO Issued (Expire Date: 04-15-2026) 10/17/2025 JEFFREY DURAN
TCO Issued (Expire Date: 10-12-2026) 4/15/2026 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/16/2021 MATTHEW CRAIG
Internal circulation Cleared 9/2/2021 SHEILA AHORAIAN
Miscellaneous Cleared 9/2/2021 SHEILA AHORAIAN
Excavation more than 5-ft deep Cleared 9/4/2021 CALOSHA APPROVED
Sewer availability Cleared 9/30/2021 CARLOS AGUILERA
Fire Marshal Fire Life Safety Cleared 11/1/2021 MENOA AGHAJANI
Trees in Parkway Cleared 11/17/2021 ADALBERTO VERA
Green Code Cleared 1/25/2022 MICHAEL AYERS
Frnt yard landscape/Water mgmt Cleared 2/16/2022 LAUREN PADICK
ZA Case Cleared 2/16/2022 LAUREN PADICK
Tract Map conditions Cleared 2/17/2022 LAUREN PADICK
DAS Clearance Cleared 5/31/2022 RARES BODEA
Highway dedication Cleared 6/6/2022 LEE GUILBEAUX
Permit Cleared 6/6/2022 LEE GUILBEAUX
Low Impact Development Cleared 6/13/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/13/2022 DAGOVERTO GUERRERO
Address approval Cleared 6/14/2022 LEE GUILBEAUX
GPI Written Notices Cleared 7/21/2022 RARES BODEA
Grading Pre-Inspection Cleared 7/21/2022 RARES BODEA

Contact Information

Architect Stockton,, Kenneth; Lic. No.: C19870 16461 SHERMAN WAY #100      VAN NUYS, CA 91406
Contractor Becker General Contractors Inc; Lic. No.: 706409-B P O BOX 643140      LOS ANGELES, CA 90064
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/26/2023 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/27/2023 Conditional Approval CAMERON CHABAN
Reinforced Concrete Frame 7/27/2023 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/28/2023 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 7/28/2023 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 7/31/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/1/2023 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 8/2/2023 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 8/9/2023 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/10/2023 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 8/28/2023 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 8/28/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/29/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/21/2023 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 9/21/2023 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 9/22/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/25/2023 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 10/26/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 10/30/2023 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 11/6/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 11/13/2023 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 1/17/2024 Approved JOHN KITCKO
Deputy Fireproofing 1/17/2024 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Partial Inspection JEFFREY FULTON
Deputy Fireproofing 1/22/2024 Conditional Approval JEFFREY FULTON
Deputy Fireproofing 1/29/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 4/23/2024 Partial Inspection ROBERT DAVIS
Green Building Rough 4/23/2024 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval DANIEL VARNUM
Pre-Inspection 8/20/2024 Partial Approval ROBERT DAVIS
Insulation 8/29/2024 Partial Approval GREGORY POMISH
Drywall Nailing 9/3/2024 Partial Approval ROBERT DAVIS
Green Building Rough 9/3/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 9/19/2024 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 9/19/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 9/19/2024 Partial Approval ROBERT DAVIS
Pre-Inspection 10/11/2024 Partial Inspection ROBERT DAVIS
Insulation 10/21/2024 Not Ready for Inspection GREGORY POMISH
Insulation 10/24/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 11/8/2024 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 11/12/2024 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 11/22/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 12/20/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 12/23/2024 Approved ROBERT DAVIS
Pre-Inspection 2/14/2025 Corrections Issued ROBERT DAVIS
Insulation 2/21/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 2/26/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 3/3/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/4/2025 Conditional Approval ROBERT DAVIS
Pre-Inspection 3/7/2025 Partial Approval GREGORY POMISH
Insulation 3/14/2025 Partial Approval ROBERT DAVIS
Wood Frame 3/14/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 3/18/2025 Partial Approval ROBERT DAVIS
Insulation 3/18/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 3/26/2025 Partial Approval ROBERT DAVIS
Insulation 3/26/2025 Approved ROBERT DAVIS
Drywall Nailing 4/1/2025 Partial Approval ROBERT DAVIS
Pre-Inspection 4/3/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 4/14/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 4/17/2025 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 4/29/2025 Partial Inspection GREGORY POMISH
Light Gage Steel Frame 5/7/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 5/9/2025 Approved ROBERT DAVIS
T-Bar Ceiling 5/19/2025 Partial Approval ROBERT DAVIS
T-Bar Ceiling 5/29/2025 Approved ROBERT DAVIS
Deputy Reinf. Concrete 6/25/2025 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/25/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/27/2025 Conditional Approval ROBERT DAVIS
Pre-Inspection 9/18/2025 Partial Approval ROBERT DAVIS
Final 10/15/2025 OK for TCO ROBERT DAVIS
Footing/Foundation/Slab 10/15/2025 Approved ROBERT DAVIS
Green Building Final 10/15/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved ROBERT DAVIS
Smoke Detectors 10/15/2025 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 10/15/2025 Approved ROBERT DAVIS
Wood Frame 10/15/2025 Approved ROBERT DAVIS
Special/Order Compliance 3/17/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 3/19/2026 Partial Inspection ROBERT DAVIS