13642 W RELIANCE ST 91331
Certificate Information: 13642 W RELIANCE ST 91331
- Application / Permit
- 21010-20000-00038
- Plan Check / Job No.
- B21VN00056
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 40'1"X26' ACCESSORY DWELLING UNIT PER ORD #186,481.
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 1/23/2021 | HAYATO TSUCHIYA |
| Quality Review Completed | 1/29/2021 | STEVEN KIM |
| Applicant returned to address corrections | 8/1/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 8/3/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/30/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | ROBERT GOLD |
| CofO Issued | 10/24/2023 | RUBEN SALAS |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2021 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 4/3/2021 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 4/9/2021 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 5/7/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 7/7/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 3/17/2022 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/31/2022 | Approved | GREGG CUMMINGS |
| Sewer | 7/21/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/28/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 8/2/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/10/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/10/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 8/10/2022 | Partial Approval | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/10/2022 | Approved | GREGG CUMMINGS |
| Deputy Wood Construction | 8/11/2022 | Conditional Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/16/2022 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 8/16/2022 | Approved | WILLIAM WREN |
| Insulation | 8/16/2022 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 8/19/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/19/2022 | Approved | WILLIAM WREN |
| Insulation | 8/23/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 10/25/2022 | Approved | GREGG CUMMINGS |
| Final | 8/8/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/12/2023 | Corrections Issued | DAVID MATSON |
| Green Building Final | 9/12/2023 | Approved | DAVID MATSON |
| Service/Power Release | 9/12/2023 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 9/12/2023 | Approved | DAVID MATSON |
| Final | 9/22/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 9/22/2023 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 10/4/2023 | Approved | GREGG CUMMINGS |
| Final | 10/18/2023 | OK to Issue CofO | ROBERT GOLD |