12975 W MONTAGUE ST 91331

Certificate Information: 12975 W MONTAGUE ST 91331

Application / Permit
21010-20000-00024
Plan Check / Job No.
B21VN00032
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-3" X 27'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 2/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 JENNIFER LEE
Corrections Issued 2/1/2021 JENNIFER LEE
Plan Check Approved 8/9/2021 JENNIFER LEE
Issued 8/18/2021 APPLICANT
Building Plans Picked Up 8/19/2021 APPLICANT
CofO in Progress 2/17/2023 MICHEL ABAJAN
Permit Finaled 2/21/2023 RONALD MYRICK
CofO Issued 2/21/2023 RONALD MYRICK
Permit Finaled 2/21/2023 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2021 GUILLERMO PETRA
Construction near power lines Cleared 7/22/2021 RIDWAN HARDY
Low Impact Development Cleared 7/30/2021 JORGE MEJIA LEMUS
Address approval Cleared 7/31/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/31/2021 LEE GUILBEAUX
Sewer availability Cleared 7/31/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD   SUITE 227    ENCINO, CA 91436

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/3/2022 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/18/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Partial Approval MICHEL ABAJAN
Wood Frame 5/25/2022 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 6/9/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 6/9/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 6/17/2022 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 6/17/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/22/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/26/2022 Approved MICHEL ABAJAN
Green Building Rough 8/26/2022 Approved MICHEL ABAJAN
HVAC-Rough 8/26/2022 Approved MICHEL ABAJAN
Underground Mechanical 8/26/2022 Approved MICHEL ABAJAN
Insulation 9/14/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/14/2022 Approved MICHEL ABAJAN
Drywall Nailing 9/30/2022 Approved MICHEL ABAJAN
Final 1/27/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 1/27/2023 Approved GREGG CUMMINGS
Green Building Final 1/27/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 1/27/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 1/27/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/17/2023 Approved MICHEL ABAJAN
Final 2/17/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 2/17/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/17/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 2/17/2023 Approved MICHEL ABAJAN