7725 N ETIWANDA AVE 91335

Certificate Information: 7725 N ETIWANDA AVE 91335

Application / Permit
21010-20000-00013
Plan Check / Job No.
B21VN00017
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED 42' X 20' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c),(d) AND (g). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 GURUNATH NESARAJAH
Corrections Issued 1/17/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 2/23/2022 GURUNATH NESARAJAH
Plan Check Approved 5/9/2022 GURUNATH NESARAJAH
Issued 5/9/2022 APPLICANT
Building Plans Picked Up 5/12/2022 APPLICANT
CofO in Progress 4/25/2023 JEFFREY BULL
Permit Finaled 5/2/2023 JOHN JANSON
CofO Issued 5/2/2023 JOHN JANSON
Permit Finaled 5/2/2023 JOHN JANSON

Permit Application Clearance Information

"Q" conditions Cleared 1/20/2021 LAUREN PADICK
Address approval Cleared 1/20/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 ADRIAN CASTRO
Sewer availability Cleared 1/20/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 2/26/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/23/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/17/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2022 Approved TROY SANDERS
Footing/Foundation/Slab 10/21/2022 Approved TROY SANDERS
PLUMBING-Rough 10/21/2022 Partial Approval TROY SANDERS
Pre-Inspection 10/21/2022 Approved TROY SANDERS
Underground Mechanical 10/21/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 12/1/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 12/1/2022 Approved JEFFREY BULL
Green Building Rough 12/1/2022 Approved JEFFREY BULL
PLUMBING-Rough 12/1/2022 Approved JEFFREY BULL
Pre-Inspection 12/1/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 12/1/2022 Approved JEFFREY BULL
HVAC-Rough 12/27/2022 Approved JEFFREY BULL
Insulation 12/27/2022 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 12/27/2022 Approved JEFFREY BULL
Drywall Nailing 1/9/2023 Approved SEAN HAUPT
Final 3/30/2023 Corrections Issued JEFFREY BULL
Green Building Final 3/30/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 3/30/2023 Not Ready for Inspection JEFFREY BULL
Smoke Detectors 3/30/2023 Approved JEFFREY BULL
Final 4/4/2023 Not Ready for Inspection JEFFREY BULL
Service/Power Release 4/4/2023 Not Ready for Inspection JEFFREY BULL
Special/Order Compliance 4/4/2023 Partial Inspection MORRIS JACKSON
Final 4/24/2023 OK to Issue CofO JEFFREY BULL
Service/Power Release 4/24/2023 Approved JEFFREY BULL