8204 N LENNOX AVE 91402

Certificate Information: 8204 N LENNOX AVE 91402

Application / Permit
21010-20000-00004
Plan Check / Job No.
B21VN00005
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED ACCESSORY DWELLING UNIT (28'10"X20') PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 HAYATO TSUCHIYA
Corrections Issued 1/17/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 7/19/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 8/11/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 9/1/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 11/30/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 12/20/2021 HAYATO TSUCHIYA
Plan Check Approved 12/28/2021 HAYATO TSUCHIYA
Issued 12/30/2021 APPLICANT
Building Plans Picked Up 1/3/2022 APPLICANT
CofO in Progress 11/7/2023 DAVID MATSON
CofO Issued 11/18/2023 RUBEN SALAS
Permit Finaled 11/18/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/17/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/17/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/17/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 5/25/2021 RIDWAN HARDY
Low Impact Development Cleared 6/29/2021 TA ANH
Roof/Waste drainage to street Cleared 7/12/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/15/2021 JOHN CONNEALLY

Contact Information

No Data Available.

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/8/2022 Partial Approval DAVID MATSON
Footing/Foundation/Slab 6/15/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 6/24/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/20/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 7/20/2022 Approved GREGG CUMMINGS
Special/Order Compliance 7/20/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/25/2022 No Access for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 No Access for Inspection GREGG CUMMINGS
PLUMBING-Rough 8/25/2022 No Access for Inspection GREGG CUMMINGS
Sewer 8/25/2022 No Access for Inspection GREGG CUMMINGS
Wood Frame 8/25/2022 No Access for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/29/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/29/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 8/29/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/29/2022 Approved GREGG CUMMINGS
Sewer 8/29/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 8/31/2022 Approved WILLIAM WREN
ELECTRICAL-Rough 8/31/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Approved WILLIAM WREN
Green Building Rough 8/31/2022 Approved WILLIAM WREN
HVAC-Rough 8/31/2022 Approved WILLIAM WREN
Verify Sprinkler Sign Off 8/31/2022 Approved WILLIAM WREN
Insulation 9/12/2022 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 9/12/2022 Approved WILLIAM WREN
Insulation 9/15/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 9/15/2022 Partial Approval ASHLEY THOMPSON
Drywall Nailing 9/21/2022 Approved WILLIAM WREN
Final 4/14/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 4/14/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 4/14/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 4/14/2023 Approved GREGG CUMMINGS
Final 10/11/2023 OK to Issue CofO DAVID MATSON
Service/Power Release 10/11/2023 Approved DAVID MATSON