509 1/4-1/2 N AVENUE 50 90042
Certificate Information: 509 1/4-1/2 N AVENUE 50 90042
- Application / Permit
- 21010-10002-05833
- Plan Check / Job No.
- B23LA07606
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ATTN: SUPPLEMENTAL TO 21010-10000-05833 for the change of new scope of work of ADU into TWO DETACHED ADU per State Law GCS 65852.2(e)(1)(D) and LAMC 12.22 A 33(c)(d)&(g).
- Permit Issued
- Issued on 3/18/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | ZAW HAN |
| Corrections Issued | 5/4/2023 | ZAW HAN |
| Quality Review Completed | 5/9/2023 | RODOLFO ARIAS |
| Building Plans Picked Up | 5/10/2023 | APPLICANT |
| Applicant returned to address corrections | 7/27/2023 | ZAW HAN |
| Applicant returned to address corrections | 8/16/2023 | ZAW HAN |
| Applicant returned to address corrections | 8/31/2023 | ZAW HAN |
| Applicant returned to address corrections | 10/19/2023 | ZAW HAN |
| Applicant returned to address corrections | 11/2/2023 | ZAW HAN |
| Applicant returned to address corrections | 12/14/2023 | ZAW HAN |
| Applicant returned to address corrections | 1/3/2024 | ZAW HAN |
| Plan Check Approved | 2/14/2024 | ZAW HAN |
| Issued | 3/18/2024 | APPLICANT |
| Permit Finaled | 6/18/2025 | NICHOLAS LOPEZ |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2023 | CELINA MORENO |
| Highway dedication | Cleared | 6/3/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2023 | CELINA MORENO |
| Sewer availability | Cleared | 6/8/2023 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/9/2023 | SERGIO VALENZUELA |
| Hydrant and Access approval | Cleared | 6/16/2023 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 6/16/2023 | RICARDO BOHORQUEZ |
| Low Impact Development (LID) | Cleared | 6/28/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | CELINA MORENO |
| Miscellaneous | Cleared | 7/12/2023 | CLAUDE GOODING |
| GPI Written Notices | Cleared | 7/13/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Saddick Construction Company Inc; Lic. No.: 751864-B | 1601 COLINA DR GLENDALE, CA 91208 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/23/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/29/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/30/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 8/8/2024 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/9/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/16/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 10/16/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/16/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 10/28/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/28/2024 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 10/30/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/13/2024 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 12/2/2024 | Approved | THOMAS LOGRASSO |
| Sewer | 12/2/2024 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 12/24/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Final | 2/28/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 3/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 3/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 3/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 3/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Service/Power Release | 3/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Smoke Detectors | 3/27/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/1/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 4/1/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Final | 4/1/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 4/1/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 4/1/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Service/Power Release | 4/1/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/2/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 5/2/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 5/27/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Service/Power Release | 5/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 6/18/2025 | Permit Finaled | NICHOLAS LOPEZ |
| Service/Power Release | 6/18/2025 | Not Required | NICHOLAS LOPEZ |