970 W 8TH ST 90731
Certificate Information: 970 W 8TH ST 90731
- Application / Permit
- 21010-10001-06764
- Plan Check / Job No.
- B22LA18543
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Supplemental permit to 21010-10000-06764 for structural changes, relocate FAU and wtaer heater
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | MONICA RAMIREZ |
| Corrections Issued | 10/5/2022 | MONICA RAMIREZ |
| Quality Review Completed | 10/6/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/2/2022 | MONICA RAMIREZ |
| Plan Check Approved | 11/8/2022 | MONICA RAMIREZ |
| No Progress | 11/10/2022 | MONICA RAMIREZ |
| Plan Check Approved | 11/10/2022 | STANLEY RAAP |
| Issued | 11/15/2022 | APPLICANT |
| Permit Finaled | 10/30/2023 | JAMES CHAVEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Approved | JAMES CHAVEZ |
| Pre-Inspection | 1/20/2023 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 1/20/2023 | Not Ready for Inspection | ANSON MAGLASANG |