1936 N HANCOCK ST 90031

Certificate Information: 1936 N HANCOCK ST 90031

Application / Permit
21010-10001-01470
Plan Check / Job No.
B21LA21256
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY DETACHED 1-CAR GARAGE WITH ADU.
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/15/2021 JOE VO
Assigned to Plan Check Engineer 11/16/2021 JOE VO
Corrections Issued 11/16/2021 JOE VO
Applicant returned to address corrections 2/17/2022 JOE VO
Plan Check Approved 5/11/2022 JOE VO
Issued 5/18/2022 APPLICANT
Permit Finaled-Status Void 2/22/2023 MARK VAN SLOOTEN
Re-Activate Permit 4/5/2023 MARK VAN SLOOTEN
Permit Finaled 11/18/2024 DANIEL SANCHEZ
CofO Issued 11/18/2024 DANIEL SANCHEZ
Permit Finaled 11/18/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 5/3/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 5/3/2022 AMAAN MALIK
Sewer availability Cleared 5/3/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 5/6/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/17/2022 Corrections Issued MARK VAN SLOOTEN
Footing/Foundation/Slab 11/8/2022 Approved MARK VAN SLOOTEN
Rough-Elec/Plmb/HVAC 11/8/2022 Corrections Issued MARK VAN SLOOTEN
BUILDING-Rough-Frame 11/9/2022 Approved MARK VAN SLOOTEN
Green Building Rough 11/9/2022 Approved MARK VAN SLOOTEN
Verify Sprinkler Sign Off 11/9/2022 Approved MARK VAN SLOOTEN
Final 2/13/2023 Conditional Approval MARK VAN SLOOTEN
Green Building Final 2/13/2023 Approved MARK VAN SLOOTEN
Service/Power Release 2/13/2023 Approved MARK VAN SLOOTEN
Smoke Detectors 2/13/2023 Approved MARK VAN SLOOTEN
Final 2/16/2023 Conditional Approval MARK VAN SLOOTEN
Final 2/22/2023 Partial Approval MARK VAN SLOOTEN
Rough-Elec/Plmb/HVAC 1/4/2024 Corrections Issued DANIEL DELACRUZ
ELECTRICAL-Rough 4/3/2024 Approved DANIEL DELACRUZ
Final 4/3/2024 Not Ready for Inspection DANIEL DELACRUZ
HVAC-Rough 4/3/2024 Approved DANIEL DELACRUZ
PLUMBING-Rough 4/3/2024 Approved DANIEL DELACRUZ
ELECTRICAL-Final 4/29/2024 Approved DANIEL DELACRUZ
HVAC-Final 4/29/2024 Approved DANIEL DELACRUZ
HVAC-Rough 4/29/2024 Approved DANIEL DELACRUZ
PLUMBING-Final 4/29/2024 Approved DANIEL DELACRUZ
Pre-Inspection 7/22/2024 Partial Approval DANIEL DELACRUZ
Final 8/9/2024 Partial Approval DANIEL DELACRUZ
Final 10/24/2024 Partial Approval DANIEL DELACRUZ