1936 N HANCOCK ST 90031
Certificate Information: 1936 N HANCOCK ST 90031
- Application / Permit
- 21010-10001-01470
- Plan Check / Job No.
- B21LA21256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY DETACHED 1-CAR GARAGE WITH ADU.
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2021 | JOE VO |
| Assigned to Plan Check Engineer | 11/16/2021 | JOE VO |
| Corrections Issued | 11/16/2021 | JOE VO |
| Applicant returned to address corrections | 2/17/2022 | JOE VO |
| Plan Check Approved | 5/11/2022 | JOE VO |
| Issued | 5/18/2022 | APPLICANT |
| Permit Finaled-Status Void | 2/22/2023 | MARK VAN SLOOTEN |
| Re-Activate Permit | 4/5/2023 | MARK VAN SLOOTEN |
| Permit Finaled | 11/18/2024 | DANIEL SANCHEZ |
| CofO Issued | 11/18/2024 | DANIEL SANCHEZ |
| Permit Finaled | 11/18/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 5/3/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/3/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2022 | Corrections Issued | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 11/8/2022 | Approved | MARK VAN SLOOTEN |
| Rough-Elec/Plmb/HVAC | 11/8/2022 | Corrections Issued | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 11/9/2022 | Approved | MARK VAN SLOOTEN |
| Green Building Rough | 11/9/2022 | Approved | MARK VAN SLOOTEN |
| Verify Sprinkler Sign Off | 11/9/2022 | Approved | MARK VAN SLOOTEN |
| Final | 2/13/2023 | Conditional Approval | MARK VAN SLOOTEN |
| Green Building Final | 2/13/2023 | Approved | MARK VAN SLOOTEN |
| Service/Power Release | 2/13/2023 | Approved | MARK VAN SLOOTEN |
| Smoke Detectors | 2/13/2023 | Approved | MARK VAN SLOOTEN |
| Final | 2/16/2023 | Conditional Approval | MARK VAN SLOOTEN |
| Final | 2/22/2023 | Partial Approval | MARK VAN SLOOTEN |
| Rough-Elec/Plmb/HVAC | 1/4/2024 | Corrections Issued | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 4/3/2024 | Approved | DANIEL DELACRUZ |
| Final | 4/3/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| HVAC-Rough | 4/3/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 4/3/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Final | 4/29/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 4/29/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 4/29/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 4/29/2024 | Approved | DANIEL DELACRUZ |
| Pre-Inspection | 7/22/2024 | Partial Approval | DANIEL DELACRUZ |
| Final | 8/9/2024 | Partial Approval | DANIEL DELACRUZ |
| Final | 10/24/2024 | Partial Approval | DANIEL DELACRUZ |