Reinforced Concrete Frame
|
3/29/2023
|
Partial Approval
|
JULIAN CAPUCETTI
|
|
Deputy Reinf. Concrete
|
3/30/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Excavation/Setback/Form/Re-Bar
|
4/4/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/6/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
4/12/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/13/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/25/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
4/26/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
5/2/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
6/12/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Subgrade
|
6/12/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Deputy Methane Barrier
|
6/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
6/28/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
7/26/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Pre-Inspection
|
7/31/2023
|
Partial Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
8/4/2023
|
Approved
|
LARRY ARNICK
|
|
Deputy Methane Barrier
|
8/7/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
8/10/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
8/28/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
8/31/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
9/6/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
9/7/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
9/8/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
9/14/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
9/28/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
10/5/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
10/5/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
10/11/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
10/12/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
10/19/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
10/20/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
10/20/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wall Anchors
|
10/23/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
10/23/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/2/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
11/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
11/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
11/9/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
11/29/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
11/29/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/29/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
1/17/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Wood Frame
|
1/17/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
1/24/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
2/6/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
2/12/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
2/12/2024
|
Approved
|
RAFAEL CORTES
|
|
Interior/Exterior Lathing
|
2/22/2024
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
2/29/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
3/6/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
3/6/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
METHANE-Rough
|
3/6/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
3/6/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
3/12/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
3/12/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
3/15/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
3/15/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
3/20/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
3/22/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
3/22/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
3/22/2024
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/1/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
4/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/9/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/9/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/18/2024
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
4/23/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/23/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/26/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/29/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/29/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
4/30/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/30/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/3/2024
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
5/3/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/10/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
5/13/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/13/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
5/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
5/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
5/16/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
5/16/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
5/16/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
5/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
6/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/28/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
7/18/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
7/22/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/19/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
8/19/2024
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
8/22/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
8/22/2024
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
8/22/2024
|
Approved
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
8/28/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Reinforced Masonry Frame
|
9/3/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
9/12/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
9/26/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
9/27/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Masonry Wall/Backfill
|
10/22/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Reinforced Concrete Frame
|
10/22/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
12/16/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Final
|
1/13/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Pre-Inspection
|
1/13/2025
|
Approved
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
1/13/2025
|
Approved
|
RAFAEL CORTES
|
|
Pre-Inspection
|
1/14/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Final
|
2/14/2025
|
Permit Finaled
|
RAFAEL CORTES
|