1714 N FAIRFAX AVE 90046
Certificate Information: 1714 N FAIRFAX AVE 90046
- Application / Permit
- 21010-10000-06947
- Plan Check / Job No.
- B21LA24432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- NEW 2 CAR CARPORT AT REAR OF LOT. 2 OF 3
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | ADRIANA LOPEZ |
| Corrections Issued | 2/11/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 2/17/2022 | SEAN DANG |
| Applicant returned to address corrections | 4/27/2022 | ADRIANA LOPEZ |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Applicant returned to address corrections | 7/18/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 8/5/2022 | ADRIANA LOPEZ |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 4/12/2023 | STUART CHAPMAN |
| CofO Issued | 4/24/2023 | DEROLD HAUFF |
| Permit Finaled | 4/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 5/17/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/3/2022 | ROGELIO CORTES |
| GPI Written Notices | Cleared | 8/5/2022 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 8/5/2022 | ADRIANA LOPEZ |
| Miscellaneous | Cleared | 8/5/2022 | ADRIANA LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/15/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/22/2022 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/30/2022 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/8/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 3/1/2023 | Approved | RAUL BARAJAS |
| Final | 3/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Service/Power Release | 3/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 3/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 3/30/2023 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 3/30/2023 | Not Required | STUART CHAPMAN |
| Smoke Detectors | 3/30/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/3/2023 | Approved | STUART CHAPMAN |
| Final | 4/3/2023 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 4/3/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 4/3/2023 | Approved | STUART CHAPMAN |
| Final | 4/12/2023 | OK to Issue CofO | STUART CHAPMAN |